✓ MahaRERA P99000027535RERA: no litigation reportedSupreme Heights
by Supreme Builders & Developers
📍 Naigaon East, Palghar · 401208
158
Units
2025
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2025
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop90–195 ft²On request
1 BHK236 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000027535
Registered
2021-09-08
Litigation
No reported in source
Escrow Bank
—
Architect
Abhay Raut
Total FSI
2417
04
Buildings · 1 Wing(s)
Supreme Heights12 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Naigaon East
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
RAJESH HABIBBHAI PANJWANIPartner
RAJESH NIRMALKUMAR JAINPartner
ROSHAN LAL BADRILAL MALOOPartner
09
Construction Progress
54% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Podiums (if any) 0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Water Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Naigaon East
Residential · Sale
₹7,000–10,000/sqft
Commercial · Sale
₹6,500–10,000/sqft
2 BHK · Rent
₹15,000–30,000/mo
Full rates
13
Commercial Projects in Naigaon East
14
More by Supreme Builders & Developers
15
MahaRERA projects nearby in Naigaon East
?
Frequently Asked Questions
When is possession of Supreme Heights?
As per MahaRERA, proposed possession is Jun 2025.
Is Supreme Heights RERA-registered?
Yes — MahaRERA registration P99000027535, registered 2021-09-08. The current MahaRERA source record reports no litigations.
Who is the developer?
Supreme Builders & Developers — 22 projects tracked on Mumbai Property Exchange.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.