Swastik Epitome Building 2 Phase I Ground to 7 floors

📍 Behind D Mart, Palghar · 401305
🕒 Last updated Sep 2026

Swastik Epitome Building 2 Phase I Ground to 7 floors is a residential project by Hemant Ramesh Mhatre in Behind D Mart, Mumbai 401305. It is registered with MahaRERA under P99000006718 (registered 2017-08-16). The project has 182 units across 5 buildings of up to 10 floors. It offers 1, 1.5 & 2 BHK homes. MahaRERA proposed possession: Apr 2027, revised to Dec 2019.

182
Units
2027
Possession
5
Buildings
Certificate Signed
Status
Lifecycle requires verification.

Ask an advisor to verify the current project and inventory status.

Other wings & phases: Swastik Epitome Building 2 Phase II 8 to 14 floors

Next steps

About Swastik Epitome Building 2 Phase I Ground to 7 floors

Location

Swastik Epitome Building 2 Phase I Ground to 7 floors is located in Behind D Mart, Mumbai 401305, in the Palghar district.

MahaRERA record

The MahaRERA registration number is P99000006718, issued on 16 August 2017. The filing lists 5 wings: C WING with 28 units over 10 floors; D WING with 42 units over 10 floors; E WING with 28 units over 10 floors; F WING with 42 units over 10 floors; G WING with 42 units over 10 floors. Per the registration, the architect on record is En Con and the project escrow account is with Bassein Catholic Cooperative Bank Ltd. MahaRERA reports litigations on record — verify the current filing on the portal.

Construction and possession

The latest MahaRERA progress report shows foundation at 70%, structure at 100%, finishing at 93%, services at 95%. Proposed possession is Apr 2027, revised to Dec 2019.

Upcoming projects & infrastructure in Virar

take an informed decision

60 MahaRERA projects are due to hand over in Virar between 2026 and 2030; the nearest upcoming infrastructure to Swastik Epitome Building 2 Phase I Ground to 7 floors is the Virar-Alibaug Multimodal Corridor, 0.8 km away (approved).

60
MahaRERA projects handing over in the next 5 years
in Virar
New projects in Virar by possession year
1
2026
14
2027
15
2028
20
2029
10
2030

Supply is not evenly spread — one year carries about a third of it.

Metro & infrastructure near Swastik Epitome Building 2 Phase I Ground to 7 floors
In the full Virar report

🔒 Units handing over each year · price by BHK · years to absorb supply · competing projects · infra impact on prices

Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK394–415 ft²On request
1.5 BHK452–500 ft²On request
2 BHK530–623 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor

RERA record & possession

Possession (proposed)
Apr 2027
Possession (revised)
Dec 2019
MahaRERA No.
P99000006718
Data last updated
Sep 2026
Registered
2017-08-16
Litigation
Yes — see RERA
Escrow Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Architect
En Con
Total FSI
7,957

Buildings · 5 wings

182 units
C WING · 10 fl · 28 u
D WING · 10 fl · 42 u
E WING · 10 fl · 28 u
F WING · 10 fl · 42 u
G WING · 10 fl · 42 u

Location

Map data © OpenStreetMap contributors · location indicativeOpen larger map ›

Construction progress

per MahaRERA
Foundation70%
Structure100%
Finishing93%
Services95%
See all 11 stages ▾
Excavation100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and …100%
Stilt Floor100%
External plumbing and external plaster, elevation, completion of terr…95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within…95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipm…90%
Sanitary Fittings within the flats / premises90%
Podiums (if any)50%
Basement (if any)0%

Amenities

15
Aggregate area of recreational Open SpaceCommunity BuildingsElectrical meter room, sub-station, r…Energy managemcntFire protection and fire safety requi…Internal Roads & FootpathsLandscaping & Tree PlantingOpen Parking
+7 more ▾
Sewerage (Chamber, Lines, Septic Tank…Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And …Water SupplyWater conservation /Rain water harvesting

Talk to our MahaRERA advisor

🏠 Discuss what you're looking for📍 Locality & project guidance🤝 Speak to a specialist

Tell our MahaRERA advisor what you need and they'll guide you on this project.

💬 Verify current project inventory

Behind D Mart market context

Property Rates in Behind D Mart

Residential · Sale
₹10,000–45,000/sqft
Commercial · Sale
₹6,500–15,000/sqft
2 BHK · Rent
₹20,000–45,000/mo

MahaRERA projects nearby in Behind D Mart

Frequently Asked Questions

Where is Swastik Epitome Building 2 Phase I Ground to 7 floors located?

Swastik Epitome Building 2 Phase I Ground to 7 floors is in Behind D Mart, Mumbai 401305.

When is possession of Swastik Epitome Building 2 Phase I Ground to 7 floors?

As per MahaRERA, proposed possession is Apr 2027, revised to Dec 2019.

Is Swastik Epitome Building 2 Phase I Ground to 7 floors RERA-registered?

Yes — MahaRERA registration P99000006718, registered 2017-08-16. MahaRERA reports litigations on record — verify the current filing on the portal.

How many units does Swastik Epitome Building 2 Phase I Ground to 7 floors have?

MahaRERA records 182 units across 5 buildings, up to 10 floors.

Who is the developer of Swastik Epitome Building 2 Phase I Ground to 7 floors?

Hemant Ramesh Mhatre View their track record ▸

How many new projects are coming up in Virar?

60 MahaRERA-registered projects in Virar are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.

What metro and infrastructure is near Swastik Epitome Building 2 Phase I Ground to 7 floors?

Virar-Alibaug Multimodal Corridor — approved, 0.8 km away; Line 13 (Shivaji Chowk-Virar) — approved, 1.6 km away; Mumbai-Ahmedabad Bullet Train — under construction · due 2029, 1.6 km away. Timelines are as announced and can change.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

Disclaimer. Information on this page is compiled from MahaRERA registrations, public infrastructure announcements, developer materials and Mumbai Property Exchange listings. Prices, availability, possession dates and infrastructure timelines are indicative, subject to change, and updated periodically (last updated 2026-09-13). This is not an offer or an advertisement by the developer; please verify all details with the developer and on MahaRERA before deciding. Mumbai Property Exchange, MahaRERA agent A51800043517.
Are you the developer and see something wrong? Report a correction on WhatsApp — we verify and update.
SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppCall

Latest Mumbai Property News

View all news →