Possession Timeline
Proposed
Mar 2024
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK249–356 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700020918
Registered
2025-09-11
Litigation
No reported in source
Escrow Bank
—
Architect
Arc Designers
Total FSI
1987
04
Buildings · 4 Wing(s)
A Wing— floors · — units
B Wing— floors · — units
C Wing5 floors · 22 units
D Wing5 floors · 28 units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Shirgaon
19.150475000000000,73.234687000000000
19.150475000000000,73.234687000000000
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
SHREEJI ENTERPRISESNA
ARC DESIGNERSArchitect
09
Construction Progress
71% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
10
Amenities
Internal Roads & FootpathsOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Shreeji Enterprises
15
MahaRERA projects nearby in Shirgaon
Mohan Willows Iii492 unitsTrident Vrindavan244 unitsKrishna Nayan Complex Phase I171 unitsShreeji Iconic161 unitsSatyam Sheela Wing F141 unitsShreeji Landmark Nx140 unitsVed Heights140 unitsShubh Vinayak Savarkar129 unitsPARIJATAK PHASE I A AND B WING128 unitsShivshakti Oasis121 unitsShubh Vastu Phase Iii112 unitsShreeji Landmark Phase Ii111 units
?
Frequently Asked Questions
When is possession of Vastu Vatika?
As per MahaRERA, proposed possession is Mar 2024.
Is Vastu Vatika RERA-registered?
Yes — MahaRERA registration P51700020918, registered 2025-09-11. The current MahaRERA source record reports no litigations.
Who is the developer?
Shreeji Enterprises — 36 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.