Project Information

RERA Certificate No.
P51800035019
Registration No.
REA51800105252
Registration Date
2023-11-22
Developer
GOREGAON ELECTRICAL INDUSTRIES LLP Partnership
Project Bank
HDFC BANK
Proposed Possession
2028-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
4835.51 sq.m
Total FSI
19075.82
Approved FSI
14675.82
MahaRERA QR
VIVAN
MahaRERA — P51800035019
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
⬇️Basements1
📅Completion2028-12-31
🏗️Proposed Floors26
Sanctioned26
⬇️Basements2
📅Completion2028-12-31
🏗️Proposed Floors26
Sanctioned26
⬇️Basements2
📅Completion2028-12-31
🏗️Proposed Floors26
Sanctioned26
⬇️Basements2
📅Completion2026-12-31
🏗️Proposed Floors26
Sanctioned26
⬇️Basements2
📅Completion2026-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 27.899999618530273 0 0 0
0%
1Bhk 33.599998474121094 0 0 0
0%
1Bhk 35.25 0 0 0
0%
1Bhk 35.310001373291016 0 0 0
0%
1Bhk 35.439998626708984 0 0 0
0%
1Bhk 35.75 0 0 0
0%
1Bhk 38.790000915527344 0 0 0
0%
1Bhk 39.0099983215332 0 0 0
0%
2Bhk 53.439998626708984 0 0 0
0%
2Bhk 54.939998626708984 0 0 0
0%
2Bhk 55.630001068115234 0 0 0
0%
Shop 10.710000038146973 0 0 0
0%

Sale Component In Rehab Building

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.18 1 0 1
0%
1 BHK 29.25 1 0 1
0%
1 BHK 29.33 1 0 1
0%
Shop 10.71 1 0 1
0%

Wing A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 35.31 42 0 42
0%
1 BHK 35.44 38 0 38
0%
2 BHK 53.44 21 0 21
0%
2 BHK 54.94 21 0 21
0%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.79 61 0 61
0%
1 BHK 39.01 21 0 21
0%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.79 61 14 47
23%
1 BHK 39.01 21 10 11
48%

Wing D

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 33.6 19 16 3
84%
1 BHK 35.25 42 9 33
21%
1 BHK 35.75 19 1 18
5%
2 BHK 55.63 42 19 23
45%

Construction Progress

SALE COMPONENT IN REHAB BUILDING

Basement (if any)100%

Sale Component In Rehab Building

Excavation100%

SALE COMPONENT IN REHAB BUILDING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Sale Component In Rehab Building

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%

SALE COMPONENT IN REHAB BUILDING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Sale Component In Rehab Building

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

SALE COMPONENT IN REHAB BUILDING

Plinth100%
Podiums (if any) 0%

Sale Component In Rehab Building

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90%

SALE COMPONENT IN REHAB BUILDING

Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%

Sale Component In Rehab Building

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.97%

SALE COMPONENT IN REHAB BUILDING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%

Sale Component In Rehab Building

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing97%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

WING A

Plinth100%
Podiums (if any) 80%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

WING B

Plinth100%
Podiums (if any) 80%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

WING C

Plinth100%
Podiums (if any) 80%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING C

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

WING D

Basement (if any)100%

Wing D

Excavation100%

WING D

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing D

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING D

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing D

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing25%

WING D

Plinth100%
Podiums (if any) 80%

Wing D

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING D

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Wing D

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING D

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing D

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.