List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
πŸ† Mumbai's oldest property portalSince 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
W
Windermere Building No 1 To 6βœ“ MahaRERA P51700049440βœ“ Clear

Windermere Building No 1 To 6 by A G Superstructures

πŸ“ Bhayander West, Thane Β· 401101
154
Units
2027
Possession
6
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Dec 2027
Status
New
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
2 BHK500 ftΒ²β‚Ή80 L
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700049440
Registered
2023-02-14
Litigation
None on record
Escrow Bank
ICICI BANK LIMITED
Architect
β€”
Total FSI
8848
04Buildings Β· 6 Wing(s)
Windermere Building No 18 floors Β· β€” units
Windermere Building No 28 floors Β· β€” units
Windermere Building No 38 floors Β· β€” units
Windermere Building No 48 floors Β· β€” units
Windermere Building No 58 floors Β· β€” units
Windermere Building No 68 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Bhayander West
19.2914982,72.8488962
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
A G SUPERSTRUCTURES PVT LTDNA
CONNECT FOUR DESIGN STUDIO LLPArchitect
08Availability & Pricing
TypeCarpetPriceAvail
1 BHK548 ftΒ²88.50 Lacs ++β€”
2 BHK758 ftΒ²1.25 Cr ++β€”
09Construction Progress94% avg
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor 100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
10Amenities
Swimming PoolKids Play AreaGardenClubhouseIndoor GamesMultipurpose HallGymnasiumJogging TrackSpaCCTV24x7 SecurityVideo Door PhoneIntercomPower BackupWater HarvestingParkingVisitor ParkingConcealed WiringConcealed Plumbing
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
14More by A G Superstructures
Adityaraj SpringsChembur Β· Under ConstructionAdityaraj AnchorVikhroli Β· Under ConstructionAdityaraj ParkChembur Β· Under ConstructionAdityaraj VivaSion Β· Ready to Move InAdityaraj SahyadriThane West Β· Under ConstructionAdityaraj MajesticChembur Β· Under Construction
15MahaRERA projects nearby in Bhayander West
Windermere Tower B269 unitsWindermere Tower A269 unitsMukundam250 unitsWindermere Tower C201 unitsNarmadalifestyle Building No 2 Antariksh116 unitsSneham42 unitsChandanbala41 unitsVaibhav Serenity - Wing D32 unitsWindsor Tower CVaibhav HorizonAnandam-ASuvarna Plaza
?Frequently Asked Questions
When is possession of Windermere Building No 1 To 6?

As per MahaRERA, proposed possession is Dec 2027.

Is Windermere Building No 1 To 6 RERA-registered?

Yes β€” MahaRERA registration P51700049440, registered 2023-02-14. No litigations on record.

What configurations and prices are available?

2 configuration(s), including 1 BHK of 548 sqft at 88.50 Lacs ++. See the pricing table above.

Who is the developer?

A G Superstructures β€” 6952 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Bhayander West β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’