Project Information

RERA Certificate No.
P51800055713
Registration No.
REA51800155215
Registration Date
2024-04-15
Developer
Apexbliss Infraventures Private Limited Company
Architect
Shoeb Mohammed
Project Bank
SARASWAT COOPERATIVE BANK LIMITED
Proposed Possession
2026-12-31
Units Sold
0
Project Area
2530.00 sq.m
Total FSI
12523.50
Approved FSI
2353.25
MahaRERA QR
Zennith
MahaRERA — P51800055713
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
Sanctioned9
⬇️Basements1
📅Completion2026-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Office Space30.75000
0%
Office Space41.900001525878906000
0%
Office Space73.58000183105469000
0%
Office Space82.87000274658203000
0%
Office Space88.54000091552734000
0%
Office Space89.6500015258789000
0%
Office Space156.5399932861328000
0%

24 High Zennith

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FIRST FLOOR IT UNIT40.59110
100%
FIRST FLOOR IT UNIT58.57220
100%
FIRST FLOOR IT UNIT62.27110
100%
FIRST FLOOR IT UNIT66.22220
100%
FIRST FLOOR IT UNIT72.66110
100%
FIRST FLOOR IT UNIT73.59110
100%
FIRST FLOOR IT UNIT79.33110
100%
FIRST FLOOR IT UNIT80.71330
100%
FIRST FLOOR IT UNIT119.54110
100%
GROUND FLOOR IT UNIT44.87110
100%
GROUND FLOOR IT UNIT50.0110
100%
GROUND FLOOR IT UNIT53.28110
100%
GROUND FLOOR IT UNIT54.34110
100%
GROUND FLOOR IT UNIT54.44752
71%
GROUND FLOOR IT UNIT58.57110
100%
GROUND FLOOR IT UNIT62.27211
50%
GROUND FLOOR IT UNIT75.03110
100%

Construction Progress

24 HIGH ZENNITH

Basement (if any)0%

24 High Zennith

Excavation65%

24 HIGH ZENNITH

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

24 High Zennith

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

24 HIGH ZENNITH

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

24 High Zennith

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing5%

24 HIGH ZENNITH

Plinth0%
Podiums (if any) 0%

24 High Zennith

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

24 HIGH ZENNITH

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

24 High Zennith

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

24 HIGH ZENNITH

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

24 High Zennith

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.