📞 +91 98200 30685 ✉️
RERA: A51800043517

9 RAJGIR

by M S KAVITA CONSTRUCTION COMPANY Partnership
Certificate Signed P51800029847
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800029847
Registration No.
REA51800091254
Registration Date
2024-05-22
Developer
M S KAVITA CONSTRUCTION COMPANY Partnership
Architect
Harish D Gandhi
Project Bank
AU SMALL FINANCE BANK LIMITED
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
103
Units Sold
77 (75%)
Buildings
1
Project Area
1662.70 sq.m
Total FSI
6478.58
Approved FSI
1158.40
MahaRERA QR
9 RAJGIR
MahaRERA — P51800029847
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
🏠Habitable19
🔢Total Units103
🏢Non-Residential103
⬇️Basements1
🅿️Closed Parking114
📅Completion2026-12-31

Apartment Configurations

9 Rajgir

Type Carpet (sq.ft) Total Booked Available Status
Office space 31.01 13 8 5
62%
Office space 45.2 11 6 5
55%
Office space 46.43 13 6 7
46%
Office space 47.6 11 4 7
36%
Office space 49.33 1 1 0
100%
Office space 51.19 2 2 0
100%
Office space 51.2 11 5 6
45%
Office space 51.58 13 6 7
46%
Office space 52.0 13 7 6
54%
Office space 64.38 1 1 0
100%
Office space 72.0 11 5 6
45%
Shop 666.64 1 1 0
100%

Construction Progress

9 RAJGIR

Basement (if any)97%

9 Rajgir

Excavation100%

9 RAJGIR

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%

9 Rajgir

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20%

9 RAJGIR

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%

9 Rajgir

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises15%

9 RAJGIR

Plinth97%
Podiums (if any) 95%

9 Rajgir

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises10%

9 RAJGIR

Sanitary Fittings within the flats / premises25%
Slabs of Super Structure100%

9 Rajgir

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

9 RAJGIR

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%

9 Rajgir

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth97%
X number of Podiums95%
X number of Slabs of Super Structure89%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 10%
Energy management
Fire Protection And Fire Safety Requirements 20%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.