📞 +91 98200 30685✉️
RERA: A51800043517

Avant Heritage I

by Aishwarya Avant Builders Llp Others
Certificate SignedP51800009299

Project Information

RERA Certificate No.
P51800009299
Registration No.
REA51800008856
Registration Date
2017-08-22
Developer
Aishwarya Avant Builders Llp Others
Architect
Ashutosh A. Kane
Project Bank
HDFC BANK
Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2022-06-30
Units Sold
0
Buildings
1
Project Area
3293.70 sq.m
Total FSI
9774.07
Approved FSI
8045.12
MahaRERA QR
Avant Heritage I
MahaRERA — P51800009299
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors24
Sanctioned24
🚗Open Parking30
📅Completion2018-12-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Rk27.139999389648438000
0%
1Bhk31.1200008392334000
0%
1Bhk38.2599983215332000
0%
1Rk22.520000457763672000
0%
1Rk28.860000610351562000
0%
2Bhk47.209999084472656000
0%
2Bhk52.529998779296875000
0%
3Bhk77.18000030517578000
0%
Duplex74.26000213623047000
0%

Avant Heritage I

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.1214014
0%
1 BHK38.261181099
92%
1 RK27.14211
50%
1RK22.52220
100%
1RK28.86110
100%
2 BHK47.21110
100%
2 BHK52.53220
100%
3 BHK77.18211
50%
Duplex74.26110
100%

Construction Progress

Avant Heritage I

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements100%
Landscaping & Tree Planting100%
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.