D
✓ MahaRERA P99000007801RERA: no litigation reportedDias Residency Park
by Dias Properties & Projects
📍 Sativali, Palghar · 401208
92
Units
2021
Possession
3
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: Ongoing · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2021
Revised
Jun 2021
Status
Ongoing
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop107–221 ft²On request
1 BHK295–359 ft²On request
2 BHK474–484 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000007801
Registered
2020-06-14
Litigation
No reported in source
Escrow Bank
IDBI BANK
Architect
En Con
Total FSI
4154
04
Buildings · 3 Wing(s)
Bldg No 1 Wing A16 floors · — units
Bldg No 29 floors · — units
Cfc Bldg No 47 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Sativali
19.404473579105186,72.873451149668090
19.404473579105186,72.873451149668090
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Barthol Lawrence DiasPartner
09
Construction Progress
98% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
Overall Percentage of Completion of the work done For the entire Building /Wing94%
10
Amenities
Aggregate area of recreational Open SpaceCommunity BuildingsElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Sativali
Residential · Sale
₹10,000–45,000/sqft
Commercial · Sale
₹6,500–15,000/sqft
2 BHK · Rent
₹20,000–45,000/mo
Full rates
14
More by Dias Properties & Projects
15
MahaRERA projects nearby in Sativali
?
Frequently Asked Questions
When is possession of Dias Residency Park?
As per MahaRERA, proposed possession is Jun 2021, revised to Jun 2021.
Is Dias Residency Park RERA-registered?
Yes — MahaRERA registration P99000007801, registered 2020-06-14. The current MahaRERA source record reports no litigations.
Who is the developer?
Dias Properties & Projects — 3 projects tracked on Mumbai Property Exchange.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.