Proposed Possession
2026-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
303
Units Sold
279 (92%)
Buildings
2
Project Area
5544.34 sq.m
Total FSI
31098.00
Approved FSI
26822.72
MahaRERA QR
Dosti Mezzo 22
MahaRERA — P51900026976
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors36
Sanctioned36
🏠Habitable29
🔢Total Units109
🏡Residential109
⬇️Basements3
🅿️Closed Parking224
📅Completion2025-12-30
🏗️Proposed Floors36
Sanctioned36
🏠Habitable29
🔢Total Units194
🏡Residential194
⬇️Basements3
🅿️Closed Parking231
📅Completion2025-12-30

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk49.38999938964844000
0%
2Bhk54.7400016784668000
0%
2Bhk55.959999084472656000
0%
2Bhk59.849998474121094000
0%
2Bhk60.060001373291016000
0%
2Bhk67.08000183105469000
0%
3Bhk79.52999877929688000
0%
3Bhk85.55000305175781000
0%
3Bhk86.4000015258789000
0%
3Bhk87.0999984741211000
0%
3Bhk103.76000213623047000
0%
3Bhk116.29000091552734000
0%

Dosti Mezzo 22 Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK79.53101
0%
3 BHK85.5525214
84%
3 BHK87.125196
76%
3 BHK103.7629254
86%
3 BHK116.2929281
97%

Dosti Mezzo 22 Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK49.3928226
79%
2 BHK54.7428235
82%
2 BHK55.9629254
86%
2 BHK59.8528226
79%
2 BHK60.0628226
79%
2 BHK67.0825178
68%
3 BHK86.428208
71%

Construction Progress

DOSTI MEZZO 22 WING A

Basement (if any)100%

Dosti Mezzo 22 Wing A

Excavation100%

DOSTI MEZZO 22 WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%

Dosti Mezzo 22 Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

DOSTI MEZZO 22 WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%

Dosti Mezzo 22 Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises63%

DOSTI MEZZO 22 WING A

Plinth100%
Podiums (if any) 100%

Dosti Mezzo 22 Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises25%

DOSTI MEZZO 22 WING A

Sanitary Fittings within the flats / premises39%
Slabs of Super Structure100%

Dosti Mezzo 22 Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.12%

DOSTI MEZZO 22 WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%

Dosti Mezzo 22 Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing3%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

DOSTI MEZZO 22 WING B

Basement (if any)100%

Dosti Mezzo 22 Wing B

Excavation100%

DOSTI MEZZO 22 WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%

Dosti Mezzo 22 Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

DOSTI MEZZO 22 WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%

Dosti Mezzo 22 Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises63%

DOSTI MEZZO 22 WING B

Plinth100%
Podiums (if any) 100%

Dosti Mezzo 22 Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises25%

DOSTI MEZZO 22 WING B

Sanitary Fittings within the flats / premises39%
Slabs of Super Structure100%

Dosti Mezzo 22 Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.12%

DOSTI MEZZO 22 WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%

Dosti Mezzo 22 Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing3%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure90%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.