📞 +91 98200 30685 ✉️
RERA: A51800043517

Foresta

by —
Kept in Abeyance P51800008744
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800008744
Registration No.
REA51800015842
Developer
Architect
Tej'S Consultant
Project Bank
ICICI Bank Ltd
Proposed Possession
2021-12-31
Revised Possession
2022-12-30
Extended Possession
2027-12-31
Buildings
2
Project Area
1155.65 sq.m
Total FSI
16476.21
Approved FSI
8768.13
MahaRERA QR
Foresta
MahaRERA — P51800008744
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking3
📅Completion2022-12-30
🅿️Closed Parking1
📅Completion2022-12-30

Apartment Configurations

Building 1

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 21.33 1 1 0
100%
1 BHK 26.32 23 16 7
70%
1 BHK 35.55 16 13 3
81%
1 BHK 36.3 27 24 3
89%
1RK 22.93 2 2 0
100%
1RK 24.79 2 0 2
0%
1RK 36.3 1 1 0
100%
2 BHK 48.69 33 20 13
61%
Shop 16.79 18 13 5
72%

Building 2

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.32 22 16 6
73%
1 BHK 35.55 20 17 3
85%
1 BHK 36.29 29 23 6
79%
1RK 22.93 2 1 1
50%
1RK 24.79 1 1 0
100%
1RK 36.29 4 3 1
75%
2 BHK 54.28 33 24 9
73%
Shop 13.81 6 0 6
0%

Construction Progress

Building 1

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises1%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor66%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure18%

Building 2

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises1%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor66%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure18%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.