Possession Timeline
Proposed
Dec 2023
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 RK183–259 ft²On request
Shop80–291 ft²On request
1 BHK269–302 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700020044
Registered
2021-09-09
Litigation
No reported in source
Escrow Bank
DCB BANK LIMITED
Architect
Destination Architecture Interior Designs
Total FSI
3395
04
Buildings · 3 Wing(s)
Wing A9 floors · — units
Wing B6 floors · — units
Wing C6 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Sonivali
19.175519000000000,73.259811000000000
19.175519000000000,73.259811000000000
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
A PLUS CREATIONNA
09
Construction Progress
100% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by A Plus Creation
15
MahaRERA projects nearby in Sonivali
?
Frequently Asked Questions
When is possession of Golden Corner?
As per MahaRERA, proposed possession is Dec 2023.
Is Golden Corner RERA-registered?
Yes — MahaRERA registration P51700020044, registered 2021-09-09. The current MahaRERA source record reports no litigations.
Who is the developer?
A Plus Creation — 7014 projects tracked on Mumbai Property Exchange.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.