I
Imperial Residencyβœ“ MahaRERA P99000001975βœ“ Clear

Imperial Residency by Shree Ganesh Coporation

πŸ“ Vasai, Palghar Β· 401208
51
Units
2018
Possession
2
Buildings
Certificate Signed
Status
PB
Pooja Batra Β· Senior Advisor
Mumbai Property Exchange Β· MahaRERA-registered since 2017
πŸ“ž CallπŸ’¬ WhatsApp
β˜…

Gallery

Imperial ResidencyImperial ResidencyImperial Residency
i

Overview

Harishchandra Complex is one of the project develop by Shree Ganesh Builders which is located in Vasai.
01

Possession Timeline

Proposed
Dec 2018
Revised
Dec 2018
Status
Ongoing
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK255–347 ftΒ²On request
2 BHK461–468 ftΒ²On request
1 RK3,929 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000001975
Registered
2017-07-31
Litigation
None on record
Escrow Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Architect
Himesh Gupta & Associates
Total FSI
2755
04

Buildings Β· 2 Wing(s)

B Wing5 floors Β· β€” units
C Wing - Proposed6 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Vasai
19.373481999999999,72.886993000000004
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Ajay Baijnath GuptaPartner
Gangaram Rajlingam MukundPartner
Mahendra PurohitPartner
Mahibulla Shaffi KhanPartner
Masroof Ahmed Rafique Ahmed ShaikhPartner
Mobataram Lilaji ChoudharyPartner
Mohd Afzal Haji Mohd KhanPartner
Munir Ahmed KhanPartner
09

Construction Progress

82% avg
Basement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
10

Amenities

Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
08

Property Rates in Vasai

Residential Β· Sale
β‚Ή10,000–45,000/sqft
Commercial Β· Sale
β‚Ή6,500–15,000/sqft
2 BHK Β· Rent
β‚Ή20,000–45,000/mo
14

More by Shree Ganesh Coporation

Naman XanaWorli Β· Sold OutPoddar VasundharaVile Parle East Β· Under ConstructionAvenue 9Vile Parle West Β· Under ConstructionAshirwad ResidencyGhatkopar East Β· Under ConstructionYashreeThane Β· Ready PossessionShreejee MrugarchanaMulund West Β· Ready Possession
15

MahaRERA projects nearby in Vasai

MLDC YASHWANT ORCHID PHASE I923 unitsMAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27901 unitsPEARL GARDENS656 unitsNakshatra Veda II514 unitsSunteck Beach Residences 4470 unitsSHRIPAL SATTVA - BLDG. 1431 unitsAkhand Phase 2409 unitsVIMAL CLASSIC380 unitsARMAAN LOTUS375 unitsOLYMPUS TOWERS355 unitsNAKSHATRA NIRVAANA II343 unitsNakshatra Veda340 units
?

Frequently Asked Questions

When is possession of Imperial Residency?

As per MahaRERA, proposed possession is Dec 2018, revised to Dec 2018.

Is Imperial Residency RERA-registered?

Yes β€” MahaRERA registration P99000001975, registered 2017-07-31. No litigations on record.

Who is the developer?

Shree Ganesh Coporation β€” 265 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Vasai β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί