RERA: A51800043517

JYOTI COMPLEX

by MANOJ KUMAR SINGH Individual
MahaRERA RegisteredP52000033382
๐Ÿ’ฌ WhatsApp๐Ÿ“ž Call

Project Information

RERA Certificate No.
P52000033382
Registration No.
REA52000102465
Registration Date
2022-02-16
Developer
MANOJ KUMAR SINGH Individual
Architect
Classical Designer
Project Bank
INDIAN BANK
Proposed Possession
2023-06-30
Revised Possession
1900-01-01
Extended Possession
2024-06-01
Total Units
17
Units Sold
2 (12%)
Buildings
1
Project Area
319.91 sq.m
Total FSI
474.35
Approved FSI
474.35
MahaRERA QR
JYOTI COMPLEX
MahaRERA โ€” P52000033382
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors6
โœ…Sanctioned6
๐Ÿ Habitable4
๐Ÿ”ขTotal Units17
๐ŸกResidential14
๐ŸขNon-Residential3
๐Ÿ…ฟ๏ธClosed Parking6
๐Ÿ“…Completion2023-06-30

Apartment Configurations

Jyoti Complex

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK24.27211
50%
1 BHK25.33101
0%
1 BHK45.68110
100%
2 BHK23.87202
0%
2 BHK25.19101
0%
Shop7.1101
0%
Shop8.24101
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk24.270000457763672000
0%
1Bhk25.329999923706055000
0%
1Bhk45.68000030517578000
0%
2Bhk23.8700008392334000
0%
2Bhk25.190000534057617000
0%
Shop7.099999904632568000
0%
Shop8.239999771118164000
0%

Construction Progress

JYOTI COMPLEX

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
Stilt Floor 100%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical Meter Room, Sub-Station, Receiving Station
โฌœEnergy management
โฌœFire Protection And Fire Safety Requirements
โฌœLandscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โฌœStorm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Conservation, Rain water Harvesting
โœ…Water Supply
CallWhatsApp
โœ‰๏ธ

Get in Touch

Our team will connect with you shortly

+91
๐Ÿ”’ Your details are secure with us
โšก If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now