Triton

by Jade Constructions Private Limited Company
Certificate SignedP51800031222

Project Information

RERA Certificate No.
P51800031222
Registration No.
REA51800094906
Registration Date
2021-10-11
Developer
Jade Constructions Private Limited Company
Architect
Ark Reza Kabul Architect Pvt Ltd
Project Bank
HDFC BANK
Proposed Possession
2025-07-01
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
3358.30 sq.m
Total FSI
11466.79
Approved FSI
11463.57
MahaRERA QR
Triton
MahaRERA — P51800031222
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors19
Sanctioned19
🅿️Closed Parking24
📅Completion2025-01-07
🏗️Proposed Floors18
Sanctioned18
🅿️Closed Parking1
📅Completion2025-01-07
🏗️Proposed Floors19
Sanctioned19
🅿️Closed Parking1
📅Completion2025-01-07

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3Bhk117.75000
0%
3Bhk118.86000061035156000
0%
3Bhk123.93000030517578000
0%
3Bhk125.63999938964844000
0%
3Bhk133.32000732421875000
0%
3Bhk140.64999389648438000
0%
3Bhk142.3699951171875000
0%
3Bhk156.10000610351562000
0%
3Bhk351.7900085449219000
0%
4Bhk170.38999938964844000
0%
4Bhk207.69000244140625000
0%
4Bhk239.38999938964844000
0%
4Bhk250.64999389648438000
0%
5Bhk &Amp;Amp; More269.1000061035156000
0%
Ext Area Member Flat9.75000
0%
Extention Area9.75000
0%

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK117.75211
50%
3 BHK118.86110
100%
3 BHK123.93110
100%
3 BHK133.32202
0%
4 BHK170.39110
100%
4 BHK207.69110
100%
4 BHK239.39101
0%
4 BHK250.65101
0%
Extention Area9.75110
100%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK125.64211
50%
3 BHK142.37211
50%
5 BHK & more269.1413
25%
Ext Area Member Flat9.75220
100%

Wing C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK140.65615
17%
3 BHK156.1523
40%
3 BHK351.79101
0%

Construction Progress

WING A

Basement (if any)100%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING A

Plinth100%
Podiums (if any) 100%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING B

Basement (if any)100%

Wing B

Excavation100%

WING B

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Wing B

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING B

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING B

Plinth100%
Podiums (if any) 100%

Wing B

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING B

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing B

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING B

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

WING C

Basement (if any)100%

Wing C

Excavation100%

WING C

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%

Wing C

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WING C

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%

WING C

Plinth100%
Podiums (if any) 100%

Wing C

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING C

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing C

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WING C

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station60%
Energy management
Fire Protection And Fire Safety Requirements70%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Solid Waste Management And Disposal75%
Storm Water Drains65%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water50%
Water Conservation, Rain water Harvesting50%
Water Supply50%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.