Proposed Possession
2018-12-31
Revised Possession
2018-12-31
Extended Possession
2019-12-31
Units Sold
0
Buildings
1
Project Area
366.89 sq.m
Total FSI
1853.30
Approved FSI
1853.30
MahaRERA QR
NEPTUNE SWARAJYA SECTOR 2 - B 14
MahaRERA — P51700003706
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2 Bhk 34.86000061035156 0 0 0
0%
Shop 1 43.790000915527344 0 0 0
0%
Shop 2 40.47999954223633 0 0 0
0%
Shop 3 49.880001068115234 0 0 0
0%

Sector 2 - B14

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 34.86 45 41 4
91%
SHOP 1 43.79 1 0 1
0%
SHOP 2 40.48 1 0 1
0%
SHOP 3 49.88 1 0 1
0%

Construction Progress

SECTOR 2 - B14

Basement (if any)100%

Sector 2 - B14

Excavation100%

SECTOR 2 - B14

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.86%

Sector 2 - B14

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60%

SECTOR 2 - B14

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%

Sector 2 - B14

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75%

SECTOR 2 - B14

Plinth100%
Podiums (if any) 0%

Sector 2 - B14

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises29%

SECTOR 2 - B14

Sanitary Fittings within the flats / premises29%
Slabs of Super Structure100%

Sector 2 - B14

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.74%

SECTOR 2 - B14

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%

Sector 2 - B14

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing86%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 50%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.