✓ MahaRERA P99000017353RERA: no litigation reported64
Units
2023
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Mar 2023
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop214 ft²On request
1 RK228 ft²On request
1 BHK319–360 ft²On request
2 BHK462 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000017353
Registered
2021-09-09
Litigation
No reported in source
Escrow Bank
UNION BANK OF INDIA
Architect
Odyssey Architects & Associates
Total FSI
2049
04
Buildings · 1 Wing(s)
Paramount Enclave Bldg No 029 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Palghar West
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
GANPAT RAMA MOHANKARPartner
MILIND JAGANNATH GHARATPartner
09
Construction Progress
74% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor 100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
Sanitary Fittings within the flats / premises40%
Podiums (if any) 0%
10
Amenities
Community BuildingsElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Palghar West
Residential · Sale
₹6,000–10,000/sqft
Commercial · Sale
₹6,000–7,500/sqft
2 BHK · Rent
₹10,000–20,000/mo
Full rates
14
More by Swastik Enterprises
15
MahaRERA projects nearby in Palghar West
KIARA109 unitsKANCHAN TRADE CENTRE94 unitsVeena Samrajya - Sector VIII Commercial68 unitsFIA VATIKA60 unitsRAJYOG HEIGHTS56 unitsSAMRIDDHI SQUARE50 unitsSHREEPATI MAHAERA50 unitsFIA AANGAN40 unitsSTAR SIGNATURE CITY - STAR OPAL35 unitsMADHU NEEM BUILDING NO. ONE TYPE A30 unitsSHREE DAYARAM RESIDENCY 1E28 unitsStar Roshan City Building No-5 Wing G24 units
?
Frequently Asked Questions
When is possession of Paramount Enclave Bldg 02?
As per MahaRERA, proposed possession is Mar 2023.
Is Paramount Enclave Bldg 02 RERA-registered?
Yes — MahaRERA registration P99000017353, registered 2021-09-09. The current MahaRERA source record reports no litigations.
Who is the developer?
Swastik Enterprises — 22 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.