📞 +91 98200 30685 ✉️
RERA: A51800043517

Vaikunth Cluster 3 Tower 2

by PEPL Developers Pvt Ltd Company
Certificate Signed P51700024580
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700024580
Registration No.
REA51700069129
Registration Date
2023-12-05
Developer
PEPL Developers Pvt Ltd Company
Project Bank
HDFC BANK
Proposed Possession
2026-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1239.00 sq.m
Total FSI
38952.00
Approved FSI
38952.00
MahaRERA QR
Vaikunth Cluster 3 Tower 2
MahaRERA — P51700024580
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors46
Sanctioned46
⬇️Basements1
🅿️Closed Parking263
📅Completion2026-06-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 30.0 0 0 0
0%
1Bhk 34.0 0 0 0
0%
1Bhk 36.0 0 0 0
0%
1Bhk 43.0 0 0 0
0%
2Bhk 48.0 0 0 0
0%
2Bhk 49.0 0 0 0
0%

Vind

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 30.0 184 162 22
88%
1 BHK 34.0 82 67 15
82%
1 BHK 36.0 82 58 24
71%
1 BHK 43.0 82 34 48
41%
2 BHK 48.0 164 38 126
23%
2 BHK 49.0 41 14 27
34%

Construction Progress

Vind

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.46%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate8%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises25%
Sanitary Fittings within the flats / premises45%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing35%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements 65%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 5%
Solid Waste Management And Disposal
Storm Water Drains 5%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 5%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.