Raman CapitalProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800076821
Registration No.
REA51800160473
Registration Date
2024-07-01
Developer
Shanti Developers
Architect
Mr Sanjay B Shah
Project Bank
CANARA BANK
Proposed Possession
2027-11-30
Total Units
344
Units Sold
49 (14%)
Buildings
1
Project Area
2551.20 sq.m
Total FSI
13768.43
Approved FSI
3558.73
Raman Capital
MahaRERA โ P51800076821
MahaRERA โ P51800076821
Scan to verify on MahaRERA portal
Wing-wise Details
๐๏ธProposed Floors19
โ
Sanctioned19
๐ Habitable15
๐ขTotal
Units344
๐ขNon-Residential344
Apartment Configurations
RAMAN CAPITAL
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| Office space | 24.84 | 1 | 0 | 1 | 0% |
| Office space | 27.75 | 1 | 0 | 1 | 0% |
| Office space | 118.77 | 1 | 0 | 1 | 0% |
| Rehab Office | 7.47 | 1 | 0 | 1 | 0% |
| Rehab Office | 12.31 | 1 | 0 | 1 | 0% |
| Rehab Office | 20.07 | 1 | 0 | 1 | 0% |
| Rehab Office | 23.39 | 1 | 0 | 1 | 0% |
| Rehab Office | 23.48 | 1 | 0 | 1 | 0% |
| Rehab Office | 25.52 | 1 | 0 | 1 | 0% |
| Rehab Office | 25.57 | 1 | 0 | 1 | 0% |
| Rehab Office | 26.08 | 1 | 0 | 1 | 0% |
| Rehab Office | 26.09 | 1 | 0 | 1 | 0% |
| Rehab Office | 26.72 | 1 | 0 | 1 | 0% |
| Rehab Office | 34.85 | 1 | 0 | 1 | 0% |
| Rehab Office | 35.32 | 1 | 0 | 1 | 0% |
| Rehab Office | 49.91 | 1 | 0 | 1 | 0% |
| Rehab Shop | 2.42 | 1 | 0 | 1 | 0% |
| Rehab Shop | 2.52 | 1 | 0 | 1 | 0% |
| Rehab Shop | 2.63 | 1 | 0 | 1 | 0% |
| Rehab Shop | 2.84 | 1 | 0 | 1 | 0% |
| Rehab Shop | 3.15 | 1 | 0 | 1 | 0% |
| Rehab Shop | 6.96 | 1 | 0 | 1 | 0% |
| Rehab Shop | 7.12 | 1 | 0 | 1 | 0% |
| Rehab Shop | 7.51 | 1 | 0 | 1 | 0% |
| Rehab Shop | 9.11 | 1 | 0 | 1 | 0% |
| Rehab Shop | 9.41 | 1 | 0 | 1 | 0% |
| Rehab Shop | 9.75 | 1 | 0 | 1 | 0% |
| Rehab Shop | 10.19 | 1 | 0 | 1 | 0% |
| Rehab Shop | 12.54 | 1 | 0 | 1 | 0% |
| Rehab Shop | 13.31 | 3 | 0 | 3 | 0% |
| Rehab Shop | 16.73 | 2 | 0 | 2 | 0% |
| Rehab Shop | 17.37 | 1 | 0 | 1 | 0% |
| Rehab Shop | 20.75 | 3 | 0 | 3 | 0% |
| Rehab Shop | 21.73 | 2 | 0 | 2 | 0% |
| Rehab Shop | 27.5 | 1 | 0 | 1 | 0% |
| Rehab Shop | 28.31 | 1 | 0 | 1 | 0% |
| Rehab Shop | 28.96 | 1 | 0 | 1 | 0% |
| Rehab Shop | 37.36 | 1 | 0 | 1 | 0% |
| Rehab Shop | 37.48 | 1 | 0 | 1 | 0% |
| Rehab Shop | 37.49 | 1 | 0 | 1 | 0% |
| Rehab Shop | 37.92 | 1 | 0 | 1 | 0% |
| Rehab Shop | 38.28 | 1 | 0 | 1 | 0% |
| Rehab Shop | 39.52 | 1 | 0 | 1 | 0% |
| Rehab Shop | 43.73 | 1 | 0 | 1 | 0% |
| Rehab office | 48.04 | 1 | 0 | 1 | 0% |
| Shop | 2.42 | 2 | 0 | 2 | 0% |
| Shop | 3.57 | 1 | 0 | 1 | 0% |
| Shop | 5.88 | 1 | 0 | 1 | 0% |
| Shop | 9.9 | 1 | 0 | 1 | 0% |
| Shop | 11.34 | 1 | 0 | 1 | 0% |
| Shop | 12.6 | 2 | 0 | 2 | 0% |
| Shop | 12.66 | 2 | 0 | 2 | 0% |
| Shop | 13.05 | 2 | 0 | 2 | 0% |
| Shop | 14.04 | 1 | 0 | 1 | 0% |
| Shop | 14.98 | 1 | 0 | 1 | 0% |
| Shop | 15.08 | 2 | 0 | 2 | 0% |
| Shop | 20.52 | 1 | 0 | 1 | 0% |
| Shop | 22.88 | 2 | 0 | 2 | 0% |
| Shop | 23.66 | 2 | 0 | 2 | 0% |
| Shop | 25.96 | 1 | 0 | 1 | 0% |
| Shop | 28.09 | 2 | 0 | 2 | 0% |
| Shop | 28.4 | 4 | 0 | 4 | 0% |
| Shop | 28.8 | 2 | 0 | 2 | 0% |
| Shop | 28.96 | 1 | 0 | 1 | 0% |
| Shop | 30.8 | 4 | 0 | 4 | 0% |
| Shop | 33.2 | 4 | 0 | 4 | 0% |
| Shop | 43.27 | 2 | 0 | 2 | 0% |
| Shop | 88.7 | 2 | 0 | 2 | 0% |
| Shop | 112.57 | 2 | 0 | 2 | 0% |
| Shop | 116.23 | 2 | 0 | 2 | 0% |
Construction Progress
RAMAN CAPITAL
RERA Registered Amenities
โ
Aggregate area of recreational Open Space
โฌCommunity Buildings
โ
Electrical meter room, sub-station, receiving station
โ
Energy managemcnt
โ
Fire protection and fire safety requirements
โ
Internal Roads & Footpaths
โ
Landscaping & Tree Planting
โ
Open Parking
โ
Sewerage (Chamber, Lines, Septic Tank , STP)
โ
Solid Waste Management And Disposal
โ
Storm Water Drains
โ
Street Lighting
โ
Treatment And Disposal Of Sewage And Sullage Water
โ
Water Supply
โ
Water conservation /Rain water harvesting