✓ MahaRERA P99000010882⚠ Litigation reported416
Units
2019
Possession
19
Buildings
Kept in Abeyance
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: On-Going Project · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jan 2019
Revised
Dec 2024
Status
On-Going Project
⚠ Possession revised later than originally proposed — per MahaRERA.
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Commercial148–258 ft²On request
1 RK260 ft²On request
1 BHK260–377 ft²On request
2 BHK358–545 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000010882
Registered
—
Litigation
Yes — see RERA
Escrow Bank
HDFC Bank
Architect
—
Total FSI
9587
04
Buildings · 19 Wing(s)
Tpe W/2 L Wing— floors · — units
Tppe W/3A K Wing— floors · — units
Type I/2A J Wing— floors · — units
Type I/2B D Wing— floors · — units
Type I/2B P Wing— floors · — units
Type I/3A I Wing— floors · — units
Type I/3B E Wing— floors · — units
Type I/4A W Wing— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Naigaon East
19.209420800000000,73.095577600000070
19.209420800000000,73.095577600000070
▸ Explore map & Street View — for verified buyers
09
Construction Progress
86% avgExcavation100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80%
Overall Percentage of Completion of the work done For the entire Building /Wing78%
Overall Percentage of Completion of the work done For the entire Building /Wing76%
Overall Percentage of Completion of the work done For the entire Building /Wing70%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationEnergy managementLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Naigaon East
Residential · Sale
₹7,000–10,000/sqft
Commercial · Sale
₹6,500–10,000/sqft
2 BHK · Rent
₹15,000–30,000/mo
Full rates
13
Commercial Projects in Naigaon East
14
More by Rashmi Housing
15
MahaRERA projects nearby in Naigaon East
?
Frequently Asked Questions
When is possession of Rashmi Pink City Phase I?
As per MahaRERA, proposed possession is Jan 2019, revised to Dec 2024.
Is Rashmi Pink City Phase I RERA-registered?
Yes — MahaRERA registration P99000010882. MahaRERA reports litigations on record — verify the current filing on the portal.
Who is the developer?
Rashmi Housing — 1 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.