📞 +91 98200 30685 ✉️
RERA: A51800043517

RAUNAK RESIDENCY

by UNNATHI ESTATES Partnership
Certificate Signed P51700009540
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700009540
Registration No.
REA51700014281
Registration Date
2025-07-04
Developer
UNNATHI ESTATES Partnership
Project Bank
HDFC BANK
Proposed Possession
2024-06-30
Revised Possession
2024-06-30
Extended Possession
2025-06-30
Total Units
380
Units Sold
347 (91%)
Buildings
2
Project Area
2421.41 sq.m
Total FSI
15758.34
Approved FSI
14058.34
MahaRERA QR
RAUNAK RESIDENCY
MahaRERA — P51700009540
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors27
Sanctioned27
🏠Habitable26
🔢Total Units190
🏡Residential190
🅿️Closed Parking87
📅Completion2024-12-31
🏗️Proposed Floors27
Sanctioned27
🏠Habitable26
🔢Total Units190
🏡Residential190
🅿️Closed Parking87
📅Completion2024-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1 Bhk 31.959999084472656 0 0 0
0%
1 Bhk 34.099998474121094 0 0 0
0%
1Bhk 31.959999084472656 0 0 0
0%
1Bhk 34.099998474121094 0 0 0
0%
2 Bhk 49.41999816894531 0 0 0
0%
2Bhk 49.41999816894531 0 0 0
0%

A

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.96 42 42 0
100%
1 BHK 34.1 96 94 2
98%
2 BHK 49.42 52 41 11
79%

B

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 31.96 42 42 0
100%
1 BHK 34.1 96 95 1
99%
2 BHK 49.42 52 37 15
71%

Construction Progress

A

Basement (if any)95%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate66%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.66%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises83%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises83%
Plinth95%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises42%
Sanitary Fittings within the flats / premises42%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth95%
X number of Podiums0%
X number of Slabs of Super Structure100%

B

Basement (if any)95%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.93%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate68%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises83%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises83%
Plinth95%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises43%
Sanitary Fittings within the flats / premises43%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing93%
X number of Basement(s) and Plinth95%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 20%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 25%
Energy management
Fire Protection And Fire Safety Requirements 25%
GYM 50%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 62%
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 50%
Water Conservation, Rain water Harvesting 50%
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.