01
Possession Timeline
Proposed
Jun 2023
Status
New Project
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop123–180 ft²On request
1 RK197–239 ft²On request
1 BHK288–359 ft²On request
2 BHK496–512 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000021713
Registered
—
Litigation
No reported in source
Escrow Bank
ANDHRA BANK
Architect
—
Total FSI
2163
04
Buildings · 2 Wing(s)
Building No 4 Wing B— floors · — units
Building Number 4 Wing A— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Boisar East
20.230800000000000,73.540200000000030
20.230800000000000,73.540200000000030
▸ Explore map & Street View — for verified buyers
09
Construction Progress
20% avgExcavation100%
X number of Basement(s) and Plinth100%
Overall Percentage of Completion of the work done For the entire Building /Wing20%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Podiums0%
X number of Slabs of Super Structure0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationEnergy managementLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Shree Balaji Enterprises
15
MahaRERA projects nearby in Boisar East
?
Frequently Asked Questions
When is possession of Shree Balaji Residency?
As per MahaRERA, proposed possession is Jun 2023.
Is Shree Balaji Residency RERA-registered?
Yes — MahaRERA registration P99000021713. The current MahaRERA source record reports no litigations.
Who is the developer?
Shree Balaji Enterprises — 269 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.