📞 +91 98200 30685✉️
RERA: A51800043517

Shree Krishna Wing A And B

by Shreem Properties Others
Certificate SignedP51800045520

Project Information

RERA Certificate No.
P51800045520
Registration No.
REA51800109148
Registration Date
2023-02-08
Developer
Shreem Properties Others
Architect
Daisaria Associates
Project Bank
INDUSIND BANK
Proposed Possession
2027-03-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
163
Units Sold
103 (63%)
Buildings
2
Project Area
6926.10 sq.m
Total FSI
22195.94
Approved FSI
12850.20
MahaRERA QR
Shree Krishna Wing A And B
MahaRERA — P51800045520
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors23
Sanctioned23
🏠Habitable20
🔢Total Units83
🏡Residential80
🏢Non-Residential3
⬇️Basements1
🚗Open Parking32
📅Completion2027-03-31
🏗️Proposed Floors23
Sanctioned23
🏠Habitable20
🔢Total Units80
🏡Residential80
⬇️Basements1
🚗Open Parking33
📅Completion2027-03-31

Apartment Configurations

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk40.06999969482422000
0%
1Bhk40.599998474121094000
0%
2Bhk51.439998626708984000
0%
2Bhk55.70000076293945000
0%
2Bhk56.47999954223633000
0%
2Bhk56.7400016784668000
0%
Shop34.970001220703125000
0%
Shop49.54999923706055000
0%
Shop61.68000030517578000
0%

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK40.07402317
57%
1 BHK40.6101
0%
2 BHK55.7392415
62%
Shop34.97110
100%
Shop49.55110
100%
Shop61.68110
100%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK40.0740931
22%
2 BHK51.44101
0%
2 BHK56.4820317
15%
2 BHK56.7419514
26%

Construction Progress

Wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises25%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises5%
Sanitary Fittings within the flats / premises5%
Slabs of Super Structure76%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums33%
X number of Slabs of Super Structure35%

Wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises25%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises5%
Sanitary Fittings within the flats / premises5%
Slabs of Super Structure75%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums33%
X number of Slabs of Super Structure35%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Swimming Pool
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.