✓ MahaRERA P51800010791RERA: no litigation reported97
Units
2008
Possession
1
Buildings
Kept in Abeyance
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: On-Going Project · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2008
Revised
Dec 2019
Status
On-Going Project
⚠ Possession revised later than originally proposed — per MahaRERA.
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 RK307 ft²On request
1 BHK371–560 ft²On request
1.5 BHK493–654 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51800010791
Registered
—
Litigation
No reported in source
Escrow Bank
hdfc
Architect
—
Total FSI
4643
04
Buildings · 1 Wing(s)
Tilak Nagar Shubham Chsl— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Mumbai
19.068535499999999,72.900320899999997
19.068535499999999,72.900320899999997
▸ Explore map & Street View — for verified buyers
09
Construction Progress
81% avgExcavation100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Slabs of Super Structure90%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%
Overall Percentage of Completion of the work done For the entire Building /Wing81%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%
X number of Podiums0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory09
Resale Flats for Sale in Mumbai
410
Flats for Rent in Mumbai
213
Commercial Projects in Mumbai
14
More by Aditya Associates
15
MahaRERA projects nearby in Mumbai
The Royal Bay579 unitsDream Ikon477 unitsGodrej Reserve Wing 3371 unitsLa Mer One Phase - II346 unitsParadise C H S Ltd341 unitsDaffodil Heights326 unitsGodrej Reserve Wing 2308 unitsNms Midas308 unitsNeelkanth Palm Avenue301 unitsPearl Blossom291 unitsGodrej Varanya Phase 1282 unitsAniraj Tower Chs Ltd274 units
?
Frequently Asked Questions
When is possession of Shubham?
As per MahaRERA, proposed possession is Jun 2008, revised to Dec 2019.
Is Shubham RERA-registered?
Yes — MahaRERA registration P51800010791. The current MahaRERA source record reports no litigations.
Who is the developer?
Aditya Associates — 45 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.