List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Paradise C H S Ltd

by Paradise Chs Ltd Society
Certificate SignedP51700079145
Paradise C H S LtdProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700079145
Registration No.
REA51700166212
Registration Date
2026-02-16
Developer
Paradise Chs Ltd Society
Architect
SOPAN PRABHU ARCHITECT & PLANNERS
Project Bank
MAHARASHTRA STATE COOPERATIVE BANK
Proposed Possession
2031-02-28
Total Units
341
Units Sold
23 (7%)
Buildings
4
Project Area
10266.00 sq.m
Total FSI
68410.38
Approved FSI
61410.38
MahaRERA QR
Paradise C H S Ltd
MahaRERA โ€” P51700079145
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable2
๐Ÿ”ขTotal Units5
๐ŸขNon-Residential5
๐Ÿ—๏ธProposed Floors42
โœ…Sanctioned42
๐Ÿ Habitable28
๐Ÿ”ขTotal Units112
๐ŸกResidential112
๐Ÿ—๏ธProposed Floors42
โœ…Sanctioned42
๐Ÿ Habitable28
๐Ÿ”ขTotal Units112
๐ŸกResidential112
๐Ÿ—๏ธProposed Floors42
โœ…Sanctioned42
๐Ÿ Habitable28
๐Ÿ”ขTotal Units112
๐ŸกResidential112

Apartment Configurations

Commercial Block

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Sale Shop160.33101
0%
Sale Shop162.12303
0%
Sale Shop219.62101
0%

Incentive Tower C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Sale 3 BHK116.661120112
0%

Rehab Tower A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Rehab 4 BHK194.1850050
0%
Sale 2 BHK81.056056
0%
Sale 4 BHK194.18606
0%

Rehab Tower B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Rehab 4 BHK194.1850050
0%
Sale 2 BHK81.056056
0%
Sale 4 BHK194.18606
0%

Construction Progress

Commercial Block

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)82%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Incentive Tower C

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)77%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Rehab Tower A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)85%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor68%

Rehab Tower B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)77%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor59%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements
โœ…Internal Roads & Footpaths
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)20%
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now