List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
πŸ† Mumbai's oldest property portalSince 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
S
βœ“ MahaRERA P51700054404βœ“ Clear

Sky Galaxy Bldg No 1 by Atree Developers

πŸ“ Badlapur West, Thane Β· 421503
90
Units
2026
Possession
3
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Dec 2026
Status
New
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop103–204 ftΒ²On request
1 BHK316–357 ftΒ²On request
2 BHK487–493 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700054404
Registered
2024-01-19
Litigation
None on record
Escrow Bank
ICICI BANK LIMITED
Architect
Samarthya Engineers
Total FSI
9500
04Buildings Β· 1 Wing(s)
Sky Galaxy Bldg No 18 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Badlapur West
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
DHAVALKUMAR PRAHALADBHAI PATELPartner
KAILAS BABAN MHASKARPartner
KISHAN SHANTILAL CHOPDAPartner
RAJESH KESHAVLAL PATELPartner
RAJESH KHIMJI CHOPDAPartner
Sanjaykumar Dinesh PatelPartner
VIPUL AMBALAL PATELPartner
09Construction Progress37% avg
Basement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
10Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Soc Office Fiteness Center Creche Driver RoomSolid Waste Management And DisposalStorm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
15MahaRERA projects nearby in Badlapur West
SWANAND VEDIKA305 unitsJagannath Paradise121 unitsVatsala Residency118 unitsP G Tower109 unitsGreen Touch104 unitsJyoti Jagannath Heritage84 unitsShiv-Kutir63 unitsShashwat Park Z-5 A And B Wing Apartment62 unitsRaj Silverstone Phase-262 unitsAudumber Chsl49 unitsJay Ramdarshan Chs Ltd42 unitsRanimaa Devi Chs41 units
?Frequently Asked Questions
When is possession of Sky Galaxy Bldg No 1?

As per MahaRERA, proposed possession is Dec 2026.

Is Sky Galaxy Bldg No 1 RERA-registered?

Yes β€” MahaRERA registration P51700054404, registered 2024-01-19. No litigations on record.

Who is the developer?

Atree Developers View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Badlapur West β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’