📞 +91 98200 30685 ✉️
RERA: A51800043517

Swiss Boulevard

by Chaurang Associates Others
Certificate Signed P51700000636
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700000636
Registration No.
REA51700004144
Registration Date
2021-09-09
Developer
Chaurang Associates Others
Architect
Nambarch
Project Bank
STATE BANK OF INDIA
Proposed Possession
2022-03-30
Revised Possession
2022-03-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
666.20 sq.m
Total FSI
2344.68
Approved FSI
594.68
MahaRERA QR
Swiss Boulevard
MahaRERA — P51700000636
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🅿️Closed Parking10
📅Completion2020-03-31
🏗️Proposed Floors7
Sanctioned7
🅿️Closed Parking10
📅Completion2020-03-31
🏗️Proposed Floors2
Sanctioned2
📅Completion1900-01-01

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 60.20000076293945 0 0 0
0%
2Bhk 67.87999725341797 0 0 0
0%
2Bhk 68.61000061035156 0 0 0
0%
3Bhk 80.3499984741211 0 0 0
0%
3Bhk 80.4800033569336 0 0 0
0%
3Bhk 93.37999725341797 0 0 0
0%
3Bhk 94.55999755859375 0 0 0
0%

Swiss Boulevard Phase 1-1St To 4Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2bhk 60.2 1 0 1
0%
2bhk 68.61 2 2 0
100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 67.88 1 0 1
0%
3 BHK 80.35 4 0 4
0%
3 BHK 93.38 3 0 3
0%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 80.48 2 0 2
0%
3 BHK 94.56 2 0 2
0%

Construction Progress

Swiss Boulevard Phase 1-1st to 4th Floor

Basement (if any)100%

Swiss Boulevard Phase 1-1St To 4Th Floor

Excavation100%

Swiss Boulevard Phase 1-1st to 4th Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Swiss Boulevard Phase 1-1St To 4Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Swiss Boulevard Phase 1-1st to 4th Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Swiss Boulevard Phase 1-1St To 4Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

Swiss Boulevard Phase 1-1st to 4th Floor

Plinth100%
Podiums (if any) 0%

Swiss Boulevard Phase 1-1St To 4Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Swiss Boulevard Phase 1-1st to 4th Floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Swiss Boulevard Phase 1-1St To 4Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Swiss Boulevard Phase 1-1st to 4th Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Swiss Boulevard Phase 1-1St To 4Th Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Swiss Boulevard Phase 2 - 5th-11th floor

Basement (if any)100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Excavation100%

Swiss Boulevard Phase 2 - 5th-11th floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Swiss Boulevard Phase 2 - 5th-11th floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

Swiss Boulevard Phase 2 - 5th-11th floor

Plinth100%
Podiums (if any) 0%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Swiss Boulevard Phase 2 - 5th-11th floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Swiss Boulevard Phase 2 - 5th-11th floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Swiss Boulevard Phase 3 - 12th and 13th floor

Basement (if any)100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Excavation100%

Swiss Boulevard Phase 3 - 12th and 13th floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Swiss Boulevard Phase 3 - 12th and 13th floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

Swiss Boulevard Phase 3 - 12th and 13th floor

Plinth100%
Podiums (if any) 100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Swiss Boulevard Phase 3 - 12th and 13th floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Swiss Boulevard Phase 3 - 12th and 13th floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.