VINAYAK SHRADDHA TOWER

by K K KRISHNAN CONSTRUCTION COMPANY PVT LTD Company
Certificate Signed P51800003341
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800003341
Registration No.
REA51800009583
Registration Date
2023-04-25
Developer
K K KRISHNAN CONSTRUCTION COMPANY PVT LTD Company
Architect
Shri Suresh Krishnan
Proposed Possession
2023-03-30
Revised Possession
2023-03-30
Extended Possession
2024-12-31
Units Sold
0
Buildings
3
Project Area
1845.27 sq.m
Total FSI
7346.70
Approved FSI
6326.90
MahaRERA QR
VINAYAK SHRADDHA TOWER
MahaRERA — P51800003341
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
📅Completion2023-03-30
🏗️Proposed Floors8
Sanctioned8
🅿️Closed Parking1
📅Completion1900-01-01
🏗️Proposed Floors17
Sanctioned17
🅿️Closed Parking36
📅Completion2023-03-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 37.43000030517578 0 0 0
0%
2Bhk 50.45000076293945 0 0 0
0%
2Bhk 51.0 0 0 0
0%
2Bhk 51.060001373291016 0 0 0
0%
2Bhk 52.119998931884766 0 0 0
0%
2Bhk 52.130001068115234 0 0 0
0%
2Bhk 54.790000915527344 0 0 0
0%
2Bhk 57.59000015258789 0 0 0
0%
2Bhk 57.599998474121094 0 0 0
0%
2Bhk 58.849998474121094 0 0 0
0%
2Bhk 74.16000366210938 0 0 0
0%
Rehab 0 0 0
0%
School 0 0 0
0%

Indirakrupa

Type Carpet (sq.ft) Total Booked Available Status
Rehab 0 0 0
0%

Municipal Primary School

Type Carpet (sq.ft) Total Booked Available Status
SCHOOL 0 0 0
0%

Vinayak Shraddha Tower

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 37.43 12 9 3
75%
2 BHK 50.45 1 1 0
100%
2 BHK 51.0 2 2 0
100%
2 BHK 51.06 1 1 0
100%
2 BHK 52.12 2 2 0
100%
2 BHK 52.13 4 1 3
25%
2 BHK 54.79 2 1 1
50%
2 BHK 57.59 2 0 2
0%
2 BHK 57.6 1 1 0
100%
2 BHK 58.85 2 0 2
0%
2 BHK 74.16 2 1 1
50%

Construction Progress

INDIRAKRUPA

Basement (if any)100%

Indirakrupa

Excavation100%

INDIRAKRUPA

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Indirakrupa

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

INDIRAKRUPA

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Indirakrupa

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

INDIRAKRUPA

Plinth100%
Podiums (if any) 0%

Indirakrupa

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

INDIRAKRUPA

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Indirakrupa

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

INDIRAKRUPA

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Indirakrupa

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

MUNICIPAL PRIMARY SCHOOL

Basement (if any)100%

Municipal Primary School

Excavation100%

MUNICIPAL PRIMARY SCHOOL

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%

Municipal Primary School

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

MUNICIPAL PRIMARY SCHOOL

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%

Municipal Primary School

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises30%
Overall Percentage of Completion of the work done For the entire Building /Wing42%

MUNICIPAL PRIMARY SCHOOL

Plinth100%
Podiums (if any) 0%

Municipal Primary School

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises20%

MUNICIPAL PRIMARY SCHOOL

Sanitary Fittings within the flats / premises20%
Slabs of Super Structure40%

Municipal Primary School

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.20%

MUNICIPAL PRIMARY SCHOOL

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%

Municipal Primary School

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing10%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure40%

VINAYAK SHRADDHA TOWER

Basement (if any)100%

Vinayak Shraddha Tower

Excavation100%

VINAYAK SHRADDHA TOWER

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%

Vinayak Shraddha Tower

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate65%

VINAYAK SHRADDHA TOWER

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%

Vinayak Shraddha Tower

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80%

VINAYAK SHRADDHA TOWER

Plinth100%
Podiums (if any) 0%

Vinayak Shraddha Tower

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%

VINAYAK SHRADDHA TOWER

Sanitary Fittings within the flats / premises80%
Slabs of Super Structure80%

Vinayak Shraddha Tower

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%

VINAYAK SHRADDHA TOWER

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%

Vinayak Shraddha Tower

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure80%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 50%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.