List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

ASTER HANS HERITAGE

by HANS REALTORS Partnership
Certificate SignedP99000080705
ASTER HANS HERITAGEProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000080705
Registration No.
REA99000168380
Registration Date
2025-06-26
Developer
HANS REALTORS Partnership
Architect
POURAJ H KORE
Project Bank
IDBI BANK
Proposed Possession
2029-01-30
Total Units
62
Units Sold
10 (16%)
Buildings
2
Project Area
2117.98 sq.m
Total FSI
3685.52
Approved FSI
3685.52
MahaRERA QR
ASTER HANS HERITAGE
MahaRERA — P99000080705
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors7
Sanctioned7
🏠Habitable7
🔢Total Units26
🏡Residential26
🏗️Proposed Floors7
Sanctioned7
🏠Habitable7
🔢Total Units36
🏡Residential36

Apartment Configurations

BULDING NO 7 A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK36.2913013
0%
2BHK46.6713013
0%

BULDING NO 7 B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK36.0606
0%
1BHK36.2912012
0%
1BHK36.32606
0%
2BHK46.6712012
0%

Construction Progress

BULDING NO 7 A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises30%
Slabs of Super Structure60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor75%

BULDING NO 7 B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor75%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths75%
Landscaping & Tree Planting50%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now