Bhagwati BelmontProject photos will appear here when available.
Project Information
RERA Certificate No.
P51700021397
Registration No.
REA51700057712
Registration Date
2021-09-08
Developer
Bhagwati Ventures Llp
Architect
Saakar Architects
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
154
Units Sold
151 (98%)
Buildings
3
Project Area
4100.00 sq.m
Total FSI
8429.45
Approved FSI
6929.45
Bhagwati Belmont
MahaRERA โ P51700021397
MahaRERA โ P51700021397
Scan to verify on MahaRERA portal
Wing-wise Details
๐๏ธProposed Floors5
โ
Sanctioned5
๐๏ธProposed Floors3
โ
Sanctioned3
๐๏ธProposed Floors29
โ
Sanctioned29
๐ Habitable29
๐ขTotal
Units154
๐กResidential154
Apartment Configurations
BHAGWATI BELMONT 28th TO 31st FLOORS PROPOSED BUT
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| TYPE 1 | 41.66 | 4 | 0 | 4 | 0% |
| TYPE 2 | 60.62 | 4 | 0 | 4 | 0% |
| TYPE 3 | 41.62 | 4 | 0 | 4 | 0% |
| TYPE 4 | 41.3 | 4 | 0 | 4 | 0% |
| TYPE 5 | 41.76 | 4 | 0 | 4 | 0% |
| TYPE 6 | 60.69 | 3 | 0 | 3 | 0% |
| TYPE 7 | 39.63 | 1 | 0 | 1 | 0% |
BHAGWATI BELMONT 32nd TO 33rd FLOORS PROPOSED BUT
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| TYPE 1 | 41.66 | 2 | 0 | 2 | 0% |
| TYPE 2 | 60.62 | 2 | 0 | 2 | 0% |
| TYPE 3 | 41.62 | 2 | 0 | 2 | 0% |
| TYPE 4 | 60.69 | 1 | 0 | 1 | 0% |
| TYPE 5 | 41.3 | 2 | 0 | 2 | 0% |
| TYPE 6 | 41.76 | 2 | 0 | 2 | 0% |
| TYPE 7 | 39.63 | 1 | 0 | 1 | 0% |
BHAGWATI BELMONT Ground TO 27th FLOORS
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| TYPE 1 | 60.69 | 15 | 15 | 0 | 100% |
| TYPE 10 | 41.62 | 18 | 18 | 0 | 100% |
| TYPE 11 | 41.3 | 18 | 15 | 3 | 83% |
| TYPE 13 | 38.59 | 10 | 10 | 0 | 100% |
| TYPE 14 | 38.31 | 12 | 12 | 0 | 100% |
| TYPE 15 | 37.98 | 1 | 1 | 0 | 100% |
| TYPE 16 | 37.68 | 1 | 1 | 0 | 100% |
| TYPE 2 | 60.62 | 18 | 16 | 2 | 89% |
| TYPE 3 | 57.12 | 1 | 1 | 0 | 100% |
| TYPE 4 | 50.04 | 11 | 4 | 7 | 36% |
| TYPE 5 | 56.4 | 1 | 1 | 0 | 100% |
| TYPE 6 | 56.33 | 1 | 1 | 0 | 100% |
| TYPE 7 | 41.76 | 18 | 18 | 0 | 100% |
| TYPE 8 | 41.66 | 18 | 18 | 0 | 100% |
| TYPE 9 | 39.63 | 12 | 9 | 3 | 75% |
| TYPE12 | 38.92 | 10 | 10 | 0 | 100% |
| UNIT 1 | 14.47 | 1 | 0 | 1 | 0% |
| UNIT 10 | 20.34 | 1 | 0 | 1 | 0% |
| UNIT 11 | 22.55 | 1 | 0 | 1 | 0% |
| UNIT 12 | 17.87 | 1 | 0 | 1 | 0% |
| UNIT 13 | 48.27 | 1 | 0 | 1 | 0% |
| UNIT 14 | 24.61 | 1 | 0 | 1 | 0% |
| UNIT 15 | 16.32 | 1 | 0 | 1 | 0% |
| UNIT 16 | 24.0 | 1 | 0 | 1 | 0% |
| UNIT 17 | 20.52 | 1 | 0 | 1 | 0% |
| UNIT 18 | 23.9 | 1 | 0 | 1 | 0% |
| UNIT 19 | 20.31 | 1 | 0 | 1 | 0% |
| UNIT 2 | 13.41 | 1 | 0 | 1 | 0% |
| UNIT 20 | 19.85 | 1 | 0 | 1 | 0% |
| UNIT 21 | 13.99 | 1 | 0 | 1 | 0% |
| UNIT 3 | 36.65 | 1 | 0 | 1 | 0% |
| UNIT 4 | 15.04 | 1 | 0 | 1 | 0% |
| UNIT 5 | 12.47 | 1 | 0 | 1 | 0% |
| UNIT 6 | 18.45 | 1 | 0 | 1 | 0% |
| UNIT 7 | 17.31 | 1 | 0 | 1 | 0% |
| UNIT 8 | 13.99 | 1 | 0 | 1 | 0% |
| UNIT 9 | 26.1 | 1 | 0 | 1 | 0% |
Construction Progress
BHAGWATI BELMONT 28th TO 31st FLOORS PROPOSED BUT
BHAGWATI BELMONT 32nd TO 33rd FLOORS PROPOSED BUT
BHAGWATI BELMONT Ground TO 27th FLOORS
RERA Registered Amenities
โ
Aggregate area of recreational Open Space
โฌCommunity Buildings
โ
Electrical meter room, sub-station, receiving station
โ
Energy managemcnt
โ
Fire protection and fire safety requirements
โฌInternal Roads & Footpaths
โ
Landscaping & Tree Planting
โฌOpen Parking
โ
Sewerage (Chamber, Lines, Septic Tank , STP)
โ
Solid Waste Management And Disposal
โ
Storm Water Drains
โฌStreet Lighting
โ
Treatment And Disposal Of Sewage And Sullage Water
โ
Water Supply
โ
Water conservation /Rain water harvesting