G
✓ MahaRERA P99000035169RERA: no litigation reported101
Units
2023
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Oct 2023
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop78–349 ft²On request
1 BHK426–435 ft²On request
2 BHK541–559 ft²On request
3 BHK972–981 ft²On request
4 BHK986–991 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P99000035169
Registered
2022-05-10
Litigation
No reported in source
Escrow Bank
AXIS BANK
Architect
Shah Gattani Consultants
Total FSI
5791
04
Buildings · 1 Wing(s)
Gokul Aura14 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Virar West
19.460448667776834,72.800935633451860
19.460448667776834,72.800935633451860
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Paresh Chimanlal MehtaPartner
Parth Bhaveshkumar MehtaPartner
09
Construction Progress
100% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Virar West
Residential · Sale
₹10,000–45,000/sqft
Commercial · Sale
₹6,500–15,000/sqft
2 BHK · Rent
₹20,000–45,000/mo
Full rates
14
More by Mehta Ventures
15
MahaRERA projects nearby in Virar West
MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27901 unitsYASHWANT AVENUE 2209 unitsVIVA CITY - A3140 unitsVIVA CITY - A4138 unitsYASHWANT PRESTIGE112 unitsSHANTI NIWAS108 unitsMAHAVIR ASHISH CO-OPERATIVE HOUSING SOCIETY LTD78 unitsYASHWANT CIRCLE70 unitsAvanti Heights70 unitsSHREE GAYATRI CHSL56 unitsHIRUBAI RESIDENCY39 unitsSHREE SHIVKRUPA CO OPERATIVE HOUSING SOCIETY LIMITED31 units
?
Frequently Asked Questions
When is possession of Gokul Aura?
As per MahaRERA, proposed possession is Oct 2023.
Is Gokul Aura RERA-registered?
Yes — MahaRERA registration P99000035169, registered 2022-05-10. The current MahaRERA source record reports no litigations.
Who is the developer?
Mehta Ventures — 47 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.