G
✓ MahaRERA P51800001671RERA: no litigation reported204
Units
2018
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: Ongoing · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
₹
Kurla — resale, rent & yield
Resale
₹24,238/sqft
median · 14 listings
Rent
₹130.0/sqft/mo
2 BHK ~₹75,000/mo
Gross yield
6.4%/yr
rent vs resale value
From MPE live listings, last 18 months · Mumbai price index ›
01
Possession Timeline
Proposed
Dec 2018
Revised
Dec 2018
Status
Ongoing
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Office369–2,624 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51800001671
Registered
2017-07-29
Litigation
No reported in source
Escrow Bank
KOTAK MAHINDRA BANK LIMITED
Architect
Enclosurre
Total FSI
8001
04
Buildings · 1 Wing(s)
Goldcrest Business Park12 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Kurla
19.089314800000000,72.907805700000000
19.089314800000000,72.907805700000000
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Swastik AssociatesNA
09
Construction Progress
82% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Podiums (if any) 0%
Stilt Floor 0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Kurla
Residential · Sale
₹55,000–75,000/sqft
Commercial · Sale
₹45,000–85,000/sqft
2 BHK · Rent
₹110,000–330,000/mo
Full rates
09
Resale Flats for Sale in Kurla
310
Flats for Rent in Kurla
411
Commercial for Sale in Kurla
312
Commercial for Lease in Kurla
314
More by Swastik Associates
15
MahaRERA projects nearby in Kurla
The Earth1245 unitsLodha Vikhroli-Signet907 unitsChandak Highscape City 1B873 unitsShraddha Vardaan723 unitsForest Hills Ph 1 At The Prestige City663 unitsPremiere By Panache579 unitsSai Shrushti521 unitsNorth Star486 unitsLaxminarayan Sra Chs Ltd474 unitsAkassh Amazonia Tower 1443 unitsPlatinum Heights435 unitsAtmosphere O2 Tower-G435 units
?
Frequently Asked Questions
When is possession of Goldcrest Business Park?
As per MahaRERA, proposed possession is Dec 2018, revised to Dec 2018.
Is Goldcrest Business Park RERA-registered?
Yes — MahaRERA registration P51800001671, registered 2017-07-29. The current MahaRERA source record reports no litigations.
Who is the developer?
Swastik Associates — 22 projects tracked on Mumbai Property Exchange. View their track record ▸