G
✓ MahaRERA PR1330002500868RERA: no litigation reported70
Units
2028
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification.
Ask an advisor to verify the current project and inventory status.
RERA record & possession
Possession (proposed)
Apr 2028
Project status
New
MahaRERA No.
PR1330002500868
Data last updated
Sep 2026
Registered
2025-09-22
Litigation
No reported in source
Escrow Bank
BANK OF BARODA
Architect
Varghese
Total FSI
4263
Buildings · 1 wing
70 unitsGOVIND HEIGHTS · 8 fl · 70 u
Location
📍 Ambarnath
19.14438919190707,73.17124405938269
19.14438919190707,73.17124405938269
▸ Explore map & Street View — for verified buyers
Construction progress
per MahaRERA50%average
Foundation60%
Structure100%
Finishing33%
Services25%
See all 11 stages ▾
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within…60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and …50%
External plumbing and external plaster, elevation, completion of terr…40%
Basement (if any)0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipm…0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Amenities
6Fire protection and fire safety requi…Landscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank…Treatment And Disposal Of Sewage And …Water SupplyWater conservation /Rain water harvesting
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventoryMore by Om Construction
MahaRERA projects nearby in Ambarnath
Chadha Residency8228 unitsPradhan Mantri Awas Yojana - Urban2352 unitsKohinoor Eden733 unitsBalaji Uphomes673 unitsMANOHAR VIKAS SHREEJI PARAISO PHASE - 2578 unitsTharwanis Meghna Montana Phase - 2541 unitsShreeji Milestone530 unitsSky Gardens At Godrej Vihaa495 unitsMohan Willows Iii492 unitsPatels Pristine432 unitsKrushna Vihar - Phase I426 unitsShreeji Square Phase I425 units
Frequently Asked Questions
When is possession of Govind Heights?
As per MahaRERA, proposed possession is Apr 2028.
Is Govind Heights RERA-registered?
Yes — MahaRERA registration PR1330002500868, registered 2025-09-22. The current MahaRERA source record reports no litigations.
Who is the developer?
Om Construction — 665 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.