List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

JASMIN

by MAHALAXMI INFRA Partnership
Certificate SignedP99000009167
JASMINProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000009167
Registration No.
REA99000017821
Registration Date
2023-09-25
Developer
MAHALAXMI INFRA Partnership
Architect
Nishant Patil Vastushilp Associates
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2021-01-31
Revised Possession
2021-01-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
4367.92 sq.m
Total FSI
3275.94
Approved FSI
3275.94
MahaRERA QR
JASMIN
MahaRERA — P99000009167
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
✅Sanctioned4
🏗️Proposed Floors4
✅Sanctioned4

Apartment Configurations

BUILDING NO 1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT25.19633
50%
FLAT31.661477
50%
FLAT33.23321
67%
FLAT41.45303
0%
FLAT47.75303
0%

BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT25.19523
40%
FLAT31.6617710
41%
FLAT33.23624
33%
FLAT47.75303
0%
FLAT47.75413
25%

Construction Progress

BUILDING NO 1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
Stilt Floor0%

BUILDING NO 2

Basement (if any)50%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth50%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths50%
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting50%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting