The World Towers - World One - Tier Ii

by Macrotech Developers Limited Company
Certificate Signed P51900008345
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51900008345
Registration No.
REA51900011272
Registration Date
2019-12-17
Developer
Macrotech Developers Limited Company
Architect
Vilas Desai & Associates
Project Bank
HDFC BANK
Proposed Possession
2018-09-30
Revised Possession
2018-09-30
Extended Possession
2020-02-25
Units Sold
0
Buildings
1
Project Area
1874.58 sq.m
Total FSI
27027.35
Approved FSI
21901.90
MahaRERA QR
The World Towers - World One - Tier Ii
MahaRERA — P51900008345
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors33
Sanctioned33
🅿️Closed Parking189
📅Completion2018-09-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
4 Bhk Villa 344.8999938964844 0 0 0
0%
4 Bhk Villa 354.8999938964844 0 0 0
0%
4Bhk Villa 332.70001220703125 0 0 0
0%
4Bhk Villa 344.79998779296875 0 0 0
0%
4Bhk Villa 354.79998779296875 0 0 0
0%

World One - Tier Ii - 44Th To 76Th Floor

Type Carpet (sq.ft) Total Booked Available Status
4 BHK Villa 332.7 8 5 3
62%
4 BHK VILLA 344.8 1 1 0
100%
4 BHK VILLA 344.9 32 32 0
100%
4 BHK VILLA 354.8 1 1 0
100%
4 BHK Villa 354.9 19 19 0
100%

Construction Progress

WORLD ONE - TIER II - 44th to 76th floor

Basement (if any)100%

World One - Tier Ii - 44Th To 76Th Floor

Excavation100%

WORLD ONE - TIER II - 44th to 76th floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

World One - Tier Ii - 44Th To 76Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

WORLD ONE - TIER II - 44th to 76th floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

World One - Tier Ii - 44Th To 76Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

WORLD ONE - TIER II - 44th to 76th floor

Plinth100%
Podiums (if any) 100%

World One - Tier Ii - 44Th To 76Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

WORLD ONE - TIER II - 44th to 76th floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

World One - Tier Ii - 44Th To 76Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

WORLD ONE - TIER II - 44th to 76th floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

World One - Tier Ii - 44Th To 76Th Floor

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Closed Parkings 100%
Community Buildings 100%
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 100%
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.