📞 +91 98200 30685 ✉️
RERA: A51800043517

OSTWAL ORCHID BUILDING NO. 9 TO 12

by ASHA ENTERPRISES Partnership
Certificate Signed P51700001968
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51700001968
Registration No.
REA51700008960
Registration Date
2021-09-09
Developer
ASHA ENTERPRISES Partnership
Architect
Tejas Consultant
Project Bank
INDUSIND BANK
Proposed Possession
2023-12-30
Revised Possession
2023-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
11612.17 sq.m
Total FSI
9098.16
Approved FSI
9098.16
MahaRERA QR
OSTWAL ORCHID BUILDING NO. 9 TO 12
MahaRERA — P51700001968
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors19
Sanctioned19
🚗Open Parking11
🅿️Closed Parking2
📅Completion2022-12-31
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking9
🅿️Closed Parking25
📅Completion2022-12-31
🏗️Proposed Floors19
Sanctioned19
🚗Open Parking11
🅿️Closed Parking73
📅Completion2022-12-31
🏗️Proposed Floors10
Sanctioned10
🚗Open Parking6
🅿️Closed Parking2
📅Completion2022-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 27.889999389648438 0 0 0
0%
1Bhk 29.329999923706055 0 0 0
0%
1Bhk 29.40999984741211 0 0 0
0%
1Bhk 29.739999771118164 0 0 0
0%
2Bhk 39.220001220703125 0 0 0
0%
2Bhk 39.630001068115234 0 0 0
0%

Ostwal Orchid Building No 10

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.33 28 28 0
100%
1 BHK 29.74 54 54 0
100%

Ostwal Orchid Building No 9

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.33 26 26 0
100%
1 BHK 29.74 28 28 0
100%

Ostwal Orchid Building No-11

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 29.33 14 14 0
100%
1 BHK 29.74 40 40 0
100%
2 BHK 39.22 14 14 0
100%
2 BHK 39.63 14 14 0
100%

Ostwal Orchid Building No-12

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 27.89 10 10 0
100%
1 BHK 29.41 10 10 0
100%

Construction Progress

OSTWAL ORCHID BUILDING NO 10

Basement (if any)100%

Ostwal Orchid Building No 10

Excavation100%

OSTWAL ORCHID BUILDING NO 10

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Ostwal Orchid Building No 10

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

OSTWAL ORCHID BUILDING NO 10

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Ostwal Orchid Building No 10

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

OSTWAL ORCHID BUILDING NO 10

Plinth100%
Podiums (if any) 100%

Ostwal Orchid Building No 10

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

OSTWAL ORCHID BUILDING NO 10

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Ostwal Orchid Building No 10

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

OSTWAL ORCHID BUILDING NO 10

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Ostwal Orchid Building No 10

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

OSTWAL ORCHID BUILDING NO 9

Basement (if any)100%

Ostwal Orchid Building No 9

Excavation100%

OSTWAL ORCHID BUILDING NO 9

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Ostwal Orchid Building No 9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

OSTWAL ORCHID BUILDING NO 9

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Ostwal Orchid Building No 9

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

OSTWAL ORCHID BUILDING NO 9

Plinth100%
Podiums (if any) 100%

Ostwal Orchid Building No 9

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

OSTWAL ORCHID BUILDING NO 9

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Ostwal Orchid Building No 9

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

OSTWAL ORCHID BUILDING NO 9

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Ostwal Orchid Building No 9

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

OSTWAL ORCHID BUILDING NO-11

Basement (if any)100%

Ostwal Orchid Building No-11

Excavation100%

OSTWAL ORCHID BUILDING NO-11

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Ostwal Orchid Building No-11

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

OSTWAL ORCHID BUILDING NO-11

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Ostwal Orchid Building No-11

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

OSTWAL ORCHID BUILDING NO-11

Plinth100%
Podiums (if any) 100%

Ostwal Orchid Building No-11

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

OSTWAL ORCHID BUILDING NO-11

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Ostwal Orchid Building No-11

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

OSTWAL ORCHID BUILDING NO-11

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Ostwal Orchid Building No-11

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

OSTWAL ORCHID BUILDING NO-12

Basement (if any)100%

Ostwal Orchid Building No-12

Excavation100%

OSTWAL ORCHID BUILDING NO-12

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Ostwal Orchid Building No-12

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

OSTWAL ORCHID BUILDING NO-12

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Ostwal Orchid Building No-12

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%

OSTWAL ORCHID BUILDING NO-12

Plinth100%
Podiums (if any) 100%

Ostwal Orchid Building No-12

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

OSTWAL ORCHID BUILDING NO-12

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Ostwal Orchid Building No-12

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

OSTWAL ORCHID BUILDING NO-12

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Ostwal Orchid Building No-12

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space 100%
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 100%
Fire Protection And Fire Safety Requirements 100%
Landscaping & Tree Planting 100%
Open Parking 100%
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
SOLAR WATER HITTING SYSTEM 100%
Solid Waste Management And Disposal
Storm Water Drains 100%
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting 100%
Water Supply 70%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.