Parinee i
by PARINEE REALTY PRIVATE LIMITED
Company
Project Information
RERA Certificate No.
P51800001904
Registration No.
REA51800006768
Registration Date
2020-06-11
Developer
PARINEE REALTY PRIVATE LIMITED Company
Project Bank
YES BANK
Proposed Possession
2021-06-30
Revised Possession
2021-06-30
Extended Possession
2024-12-31
Units Sold
0
Buildings
1
Project Area
3996.88 sq.m
Total FSI
17454.13
Approved FSI
16751.00
Parinee i
MahaRERA — P51800001904
MahaRERA — P51800001904
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors34
✅Sanctioned34
⬇️Basements3
🅿️Closed Parking304
📅Completion2020-12-31
Apartment Configurations
Parinee I
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| Office space | 53.27 | 1 | 0 | 1 | 0% |
| Office space | 53.3 | 19 | 11 | 8 | 58% |
| Office space | 53.51 | 8 | 6 | 2 | 75% |
| Office space | 53.56 | 1 | 0 | 1 | 0% |
| Office space | 53.57 | 1 | 0 | 1 | 0% |
| Office space | 53.59 | 11 | 8 | 3 | 73% |
| Office space | 53.61 | 2 | 2 | 0 | 100% |
| Office space | 54.77 | 21 | 15 | 6 | 71% |
| Office space | 54.81 | 3 | 1 | 2 | 33% |
| Office space | 55.68 | 1 | 0 | 1 | 0% |
| Office space | 55.75 | 19 | 14 | 5 | 74% |
| Office space | 58.0 | 1 | 1 | 0 | 100% |
| Office space | 64.75 | 1 | 0 | 1 | 0% |
| Office space | 64.97 | 1 | 0 | 1 | 0% |
| Office space | 66.22 | 1 | 0 | 1 | 0% |
| Office space | 67.05 | 19 | 13 | 6 | 68% |
| Office space | 68.26 | 19 | 13 | 6 | 68% |
| Office space | 68.27 | 2 | 2 | 0 | 100% |
| Office space | 71.57 | 1 | 0 | 1 | 0% |
| Office space | 76.79 | 1 | 0 | 1 | 0% |
| Office space | 78.82 | 4 | 2 | 2 | 50% |
| Office space | 78.84 | 19 | 11 | 8 | 58% |
| Office space | 80.07 | 4 | 3 | 1 | 75% |
| Office space | 80.09 | 19 | 13 | 6 | 68% |
| Office space | 82.33 | 2 | 0 | 2 | 0% |
| Office space | 82.4 | 38 | 25 | 13 | 66% |
| Office space | 92.79 | 1 | 1 | 0 | 100% |
| Office space | 118.59 | 48 | 36 | 12 | 75% |
| Office space | 140.82 | 1 | 0 | 1 | 0% |
| Office space | 195.44 | 1 | 0 | 1 | 0% |
| Office space | 199.55 | 1 | 1 | 0 | 100% |
| Office space | 467.56 | 1 | 1 | 0 | 100% |
| Office space | 468.91 | 2 | 2 | 0 | 100% |
| Restaurant | 165.01 | 1 | 1 | 0 | 100% |
| Restaurant | 176.1 | 1 | 1 | 0 | 100% |
| Restaurant | 206.22 | 1 | 0 | 1 | 0% |
| Restaurant | 210.26 | 1 | 0 | 1 | 0% |
| Restaurant | 246.33 | 1 | 0 | 1 | 0% |
| Restaurant | 246.46 | 1 | 0 | 1 | 0% |
| Restaurant | 253.84 | 1 | 0 | 1 | 0% |
| Restaurant | 256.67 | 1 | 0 | 1 | 0% |
| Restaurant | 264.93 | 1 | 0 | 1 | 0% |
| Restaurant | 271.93 | 1 | 0 | 1 | 0% |
| Restaurant | 353.67 | 1 | 0 | 1 | 0% |
| Restaurant | 354.42 | 1 | 0 | 1 | 0% |
Construction Progress
Parinee i
Parinee I
Parinee i
Parinee I
Parinee i
Parinee I
Parinee i
Parinee I
Parinee i
Parinee I
Parinee i
Parinee I
RERA Registered Amenities
✅
Aggregate area of recreational Open Space
30%
⬜
Community Buildings
✅
Electrical Meter Room, Sub-Station, Receiving Station
75%
⬜
Energy management
✅
Fire Protection And Fire Safety
Requirements
75%
✅
Landscaping & Tree Planting
100%
⬜
Open Parking
✅
Sewerage (Chamber, Lines, Septic Tank , STP)
70%
✅
Solid Waste Management And Disposal
✅
Storm Water Drains
80%
✅
Street Lighting
50%
✅
Treatment And Disposal Of Sewage And Sullage Water
50%
✅
Water Conservation, Rain water Harvesting
45%
✅
Water Supply