📞 +91 98200 30685 ✉️
RERA: A51800043517

PARK GRANDEZZA

by SHREE MAHAVIR ESTATES Partnership
Certificate Signed P51800066462
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800066462
Registration No.
REA51800160020
Registration Date
2024-06-11
Developer
SHREE MAHAVIR ESTATES Partnership
Architect
Ar Jash Desai
Project Bank
HDFC BANK
Proposed Possession
2034-02-15
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
2359.66 sq.m
Total FSI
16000.00
Approved FSI
6361.53
MahaRERA QR
PARK GRANDEZZA
MahaRERA — P51800066462
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors11
Sanctioned11
⬇️Basements2
🅿️Closed Parking31
📅Completion2034-02-15
🏗️Proposed Floors11
Sanctioned11
⬇️Basements2
🅿️Closed Parking31
📅Completion2034-02-15
🏗️Proposed Floors9
Sanctioned9
⬇️Basements2
🅿️Closed Parking31
📅Completion2034-02-15

Apartment Configurations

Wing A

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 101.26 8 0 8
0%
Existing member 101.26 15 0 15
0%

Wing B

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 101.26 4 0 4
0%
Existing member 101.26 10 0 10
0%

Wing C

Type Carpet (sq.ft) Total Booked Available Status
3 BHK 101.26 5 0 5
0%
Existing member 101.26 15 0 15
0%

Construction Progress

WING A

Basement (if any)5%

Wing A

Excavation100%

WING A

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Wing A

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

WING A

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Wing A

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

WING A

Plinth5%
Podiums (if any) 0%

Wing A

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

WING A

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Wing A

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

WING A

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing A

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Wing B

Basement (if any)5%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Plinth5%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Wing C

Basement (if any)5%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Plinth5%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.