16
Units
2022
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Jun 2022
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop129 ftΒ²On request
1 BHK266–297 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ I'm looking to buy here β€” enquire on WhatsApp
03

RERA Trust Record

MahaRERA No.
P52000021683
Registered
2021-09-08
Litigation
None on record
Escrow Bank
β€”
Architect
Atul Patel
Total FSI
539
04

Buildings Β· 1 Wing(s)

Rd Park5 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Node Ulwe
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

DOLLY AMBALAL PATELPartner
09

Construction Progress

72% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Water Supply
12

Talk to our MahaRERA advisor

🏠 Discuss what you're looking forπŸ“ Locality & project guidance🀝 Speak to a specialist

Tell our MahaRERA advisor what you need and they'll guide you on this project.

πŸ’¬ Enquire about this project on WhatsApp
13

EMI Calculator

β€”
14

More by Rd Enterprises

MonopoliDadar East Β· Under ConstructionMiraya Thane Β· Under ConstructionBliss View Thane Β· Under ConstructionRDK VivantaGhatkopar Β· Under ConstructionNavrang NavkarGoregaon West Β· Ready PossessionVardhaman PalaceGhatkopar East Β· Under Construction
15

MahaRERA projects nearby in Node Ulwe

D N Heritage49 unitsPRIME SOLITAIRE46 unitsVAIDEHI KRUPA BSAI BHAKTIBAYVIEW
?

Frequently Asked Questions

When is possession of RD PARK?

As per MahaRERA, proposed possession is Jun 2022.

Is RD PARK RERA-registered?

Yes β€” MahaRERA registration P52000021683, registered 2021-09-08. No litigations on record.

Who is the developer?

Rd Enterprises β€” 60 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Node Ulwe β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
Sponsored
New launch
Akshar Elevate, Vashi
New launch in Vashi β€” β‚Ή28,895/sq.ft
View project β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’