RERA: A51800043517

Shree Ram Krishna Garden

by Shree Salasar Sahakar Partnership
Certificate SignedP51700055880
šŸ’¬ WhatsAppšŸ“ž Call

Project Information

RERA Certificate No.
P51700055880
Registration No.
REA51700157228
Registration Date
2024-04-29
Developer
Shree Salasar Sahakar Partnership
Architect
Ptp Point To Point Consultants
Project Bank
ICICI BANK LIMITED
Proposed Possession
2029-03-31
Units Sold
0
Project Area
8602.00 sq.m
Total FSI
41374.94
Approved FSI
7280.77
MahaRERA QR
Shree Ram Krishna Garden
MahaRERA — P51700055880
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors13
āœ…Sanctioned13
šŸš—Open Parking135
šŸ…æļøClosed Parking275
šŸ“…Completion2029-03-31
šŸ—ļøProposed Floors13
āœ…Sanctioned13
šŸš—Open Parking135
šŸ…æļøClosed Parking274
šŸ“…Completion2029-03-31

Apartment Configurations

Building No 1 Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.214014
0%
1 BHK37.6514014
0%
2 BHK52.914014
0%
2 BHK55.8110010
0%
2 BHK67.25202
0%

Building No 1 Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.214014
0%
1 BHK37.6514014
0%
2 BHK52.914014
0%
2 BHK55.8110010
0%
2 BHK67.25202
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk37.20000076293945000
0%
1Bhk37.650001525878906000
0%
2Bhk52.900001525878906000
0%
2Bhk55.810001373291016000
0%
2Bhk57.54999923706055000
0%
2Bhk60.5000
0%
2Bhk67.25000
0%
2Bhk71.94000244140625000
0%

Construction Progress

BUILDING NO 1 WING A

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks17%

BUILDING NO 1 WING B

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks17%

Building No 1 Wing A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Building No 1 Wing B

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station
āœ…Energy management
āœ…Fire Protection And Fire Safety Requirements
āœ…Landscaping & Tree Planting
āœ…Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)
āœ…Solid Waste Management And Disposal
āœ…Storm Water Drains
āœ…Street Lighting
āœ…Treatment And Disposal Of Sewage And Sullage Water
āœ…Water Conservation, Rain water Harvesting
āœ…Water Supply
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now