S
✓ MahaRERA P51700051017RERA: no litigation reported82
Units
2025
Possession
2
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2025
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop156–302 ft²On request
1 BHK332–468 ft²On request
2 BHK361–562 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700051017
Registered
2026-02-12
Litigation
No reported in source
Escrow Bank
FEDERAL BANK
Architect
Bhargav Suresh Joshi
Total FSI
3137
04
Buildings · 2 Wing(s)
Shri Sadan - Building 18 floors · — units
Shri Sadan - Building 24 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Mankoli Village
19.240307,73.0415429
19.240307,73.0415429
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Shree BuildconNA
Bhargav Suresh Joshi Architect
09
Construction Progress
74% avgExcavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
Basement (if any)0%
Podiums (if any) 0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Street LightingWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Shree Buildcon
?
Frequently Asked Questions
When is possession of Shree Sadan Complex?
As per MahaRERA, proposed possession is Dec 2025.
Is Shree Sadan Complex RERA-registered?
Yes — MahaRERA registration P51700051017, registered 2026-02-12. The current MahaRERA source record reports no litigations.
Who is the developer?
Shree Buildcon — 269 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.