List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shreeji Heights Phase Ii

by Shubh Buildcon Partnership
Certificate SignedP51700031013
Want us to WhatsApp you? Enter your mobile — we’ll say hello and take it from there.
+91

Project Information

RERA Certificate No.
P51700031013
Registration No.
REA51700091791
Registration Date
2021-09-29
Developer
Shubh Buildcon Partnership
Architect
Raj Associates
Project Bank
BANK OF BARODA
Proposed Possession
2023-05-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
1568.56 sq.m
Total FSI
4568.12
Approved FSI
4568.12
MahaRERA QR
Shreeji Heights Phase Ii
MahaRERA โ€” P51700031013
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9
๐Ÿ—๏ธProposed Floors9
โœ…Sanctioned9

Apartment Configurations

WING C

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK27.3714131
93%
1BHK33.55770
100%
1BHK33.8770
100%
2BHK33.17770
100%
2BHK34.4770
100%
2BHK43.93725
29%

WING D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK42.62761
86%
2BHK44.13743
57%
2BHK45.43761
86%
2BHK45.9734
43%

Construction Progress

WING C

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

WING D

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โœ…Community Buildings
โœ…Electrical meter room, sub-station, receiving station
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now