S
✓ MahaRERA P52000027884RERA: no litigation reported9
Units
2022
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2022
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop135 ft²On request
1 RK260 ft²On request
1 BHK420–423 ft²On request
2 BHK507 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P52000027884
Registered
2021-09-08
Litigation
No reported in source
Escrow Bank
IDBI BANK
Architect
Imran Antulay And Associates
Total FSI
297
04
Buildings · 1 Wing(s)
Sneh Gandh Apartment6 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Mahad
▸ Explore map & Street View — for verified buyers
09
Construction Progress
100% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Vaibhav Dhanraj Chandorkar
15
MahaRERA projects nearby in Mahad
CKC HUB136 unitsCloud 9101 unitsLUCKY HOUSE100 unitsNITYA NIRGUN ENCLAVE90 unitsSAI SHRUSTHI82 unitsKRANTIBHUMI COOPERATIVE HOUSING SOCIETY -SILVER HEIGHT62 unitsSKYLINE RESIDENCIES59 unitsIndraprashth58 unitsRAIGAD CITY C WING53 unitsSIYA 24 K PHASE II51 unitsShinde Arcade48 unitsJAI TULJABHAVANI SAHAKARI GRUHANIRMAN SANSTHA LTD44 units
?
Frequently Asked Questions
When is possession of Sneh Gandh Apartment?
As per MahaRERA, proposed possession is Jun 2022.
Is Sneh Gandh Apartment RERA-registered?
Yes — MahaRERA registration P52000027884, registered 2021-09-08. The current MahaRERA source record reports no litigations.
Who is the developer?
Vaibhav Dhanraj Chandorkar — 16 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.