Srushtiraj TowerProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800009157
Registration No.
REA51800009574
Registration Date
2021-09-09
Developer
Chinnaiah Venkatesh Gowda Individual
Architect
Iqbal Singh
Project Bank
IDBI BANK
Proposed Possession
2027-04-25
Revised Possession
2022-12-22
Extended Possession
2025-12-25
Total Units
125
Units Sold
93 (74%)
Buildings
1
Project Area
945.12 sq.m
Total FSI
6810.00
Approved FSI
3159.09
Srushtiraj Tower
MahaRERA — P51800009157
MahaRERA — P51800009157
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors17
✅Sanctioned17
🏠Habitable17
🔢Total
Units125
🏡Residential125
Apartment Configurations
TILAK NAGAR SHANKAR CHHAYA CHS LTD
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 38.8 | 1 | 0 | 1 | 0% |
| 1BHK | 39.08 | 16 | 8 | 8 | 50% |
| 1BHK | 41.32 | 1 | 0 | 1 | 0% |
| 2BHK | 48.18 | 14 | 7 | 7 | 50% |
| 2BHK | 48.2 | 16 | 10 | 6 | 62% |
| 2BHK | 48.21 | 15 | 9 | 6 | 60% |
| 2BHK | 53.68 | 16 | 9 | 7 | 56% |
| 2BHK | 54.05 | 32 | 18 | 14 | 56% |
| 2BHK | 54.58 | 14 | 7 | 7 | 50% |
Construction Progress
TILAK NAGAR SHANKAR CHHAYA CHS LTD
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting