Vikhroli · Mumbai
The Signature Tower
Vikhroli · by Three Aces Realty
Updated Sep 2026
VikhroliPhotos from the project record · tap to enlarge
A first look at The Signature Tower
The Signature Tower is a residential project by Three Aces Realty in Vikhroli, Mumbai 400083. It is registered with MahaRERA under P51800018915 (registered 2021-09-09). The Signature Tower is sold out by the developer; ask MPE for resale or rental flats in this building. The project has 98 units across 1 building of up to 24 floors. It offers 1 & 2 BHK homes with carpet areas of 405–582 sq ft. MahaRERA proposed possession: Dec 2023.
Ask an advisor to check current resale or rental availability.
Unit configurations filed with MahaRERA (5)
The Signature Tower floor plans
1Floor plans are indicative, as shared by the developer, and subject to change.
The Signature Tower videos
About The Signature Tower
Location
The Signature Tower is located in Vikhroli, Mumbai 400083, in the Mumbai Suburban district. Across 12 recent resale listings on MPE, homes in Vikhroli have a median asking rate of ₹28,535 per sq ft, and a 2 BHK typically rents for about ₹1 Lac a month.
MahaRERA record
The MahaRERA registration number is P51800018915, issued on 9 September 2021. The registered promoter is 3 Aces Realty. The filing lists 1 wing: SHUBHALAKSHMI CHSL over 24 floors. Per the registration, the architect on record is Space Moulders and the project escrow account is with Bank Of India.
Homes and prices
The price list covers 1 BHK of 405 sq ft at ₹89.5 Lac; 2 BHK of 576–582 sq ft at ₹1.24 Cr–₹1.4 Cr (carpet area), as on 09 Jul 2026. That works out to about ₹21,500–₹24,100 per sq ft of carpet, 23% below the locality's resale median. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
The latest MahaRERA progress report shows foundation at 40%, structure at 100%, finishing at 100%, services at 100%. Proposed possession is Dec 2023.
Buyer demand in Vikhroli
In the last 90 days, buyers and tenants registered 10 requirements for Vikhroli with Mumbai Property Exchange, 3 of them to buy and 4 specifically for 1 & 2 BHK homes.
Developer's description ▾
Vikhroli market
prices, rents & ratesPrice vs locality
Vikhroli — resale, rent & yield
This project is quoted around ₹22,413/sqft — 21% below resale here.
From MPE live listings, last 18 months · Mumbai price index ›
Property rates in Vikhroli
Upcoming projects & infrastructure in Vikhroli
take an informed decision13 MahaRERA projects are due to hand over in Vikhroli between 2027 and 2031; the nearest upcoming infrastructure to The Signature Tower is the Line 4 Green, 0.7 km away (under construction · due 2027).
Supply is not evenly spread — one year carries almost half of it.
- 🚇Line 4 GreenUnder construction · due 20270.7 km
- 🚇Line 6 PinkUnder construction · due 20270.9 km
- 🚇Line 14 (Kanjurmarg-Badlapur/Ambernath)Approved1.8 km
🔒 Units handing over each year · price by BHK · years to absorb supply · competing projects · infra impact on prices
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 1 wing
Location
Construction progress
per MahaRERASee all 11 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: 2 BHK · 578 sq ft at ₹1.27 Cr (the price recorded above).
- ✓ Plinth complete45% paid by then
- ✓ Slabs complete70% paid by then
- ✓ Walls, plaster & flooring75% paid by then
- ✓ Sanitary fittings80% paid by then
- ✓ Staircases, lift wells & lobbies85% paid by then
- ✓ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹95.2 L here), released stage by stage, so your own money is about ₹31.8 L plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹82,700/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
15+7 more ▾
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Ask about resale or rental optionsResale Flats for Sale in Vikhroli
4Flats for Rent in Vikhroli
4Commercial for Lease in Vikhroli
1Commercial Projects in Vikhroli
More by Three Aces Realty
MahaRERA projects nearby in Vikhroli
Frequently Asked Questions
Where is The Signature Tower located?
The Signature Tower is in Vikhroli, Mumbai 400083.
What is the price of The Signature Tower?
The Signature Tower is sold out by the developer; ask MPE for resale or rental flats in this building.
What configurations and carpet areas does The Signature Tower offer?
1 BHK – 405 sq ft carpet; 2 BHK – 576 sq ft carpet; 2 BHK – 578 sq ft carpet; 2 BHK – 582 sq ft carpet.
When is possession of The Signature Tower?
As per MahaRERA, proposed possession is Dec 2023.
Is The Signature Tower RERA-registered?
Yes — MahaRERA registration P51800018915, registered 2021-09-09.
How many units does The Signature Tower have?
MahaRERA records 98 units across 4 buildings, up to 24 floors.
Who is the developer of The Signature Tower?
Three Aces Realty — 1 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Vikhroli?
13 MahaRERA-registered projects in Vikhroli are due for possession between 2027 and 2031, as per MahaRERA registrations. Timelines can change.
What metro and infrastructure is near The Signature Tower?
Line 4 Green — under construction · due 2027, 0.7 km away; Line 6 Pink — under construction · due 2027, 0.9 km away; Line 14 (Kanjurmarg-Badlapur/Ambernath) — approved, 1.8 km away. Timelines are as announced and can change.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.