Upper Thane - Tiara I by Lodha Developers

πŸ“ Bhiwandi, Thane Β· 421302
80
Units
2024
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Mar 2024
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
2 BHK559–604 ftΒ²On request
3 BHK68–755 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P51700018035
Registered
2021-09-09
Litigation
None on record
Escrow Bank
ICICI BANK LIMITED
Architect
Vilas Desai & Associates
Total FSI
6474
04

Buildings Β· 1 Wing(s)

Tiara I21 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Bhiwandi
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

MACROTECH DEVELOPERS LIMITEDNA
Abhishek Mangalprabhat LodhaMD
Pradeep KambleArchitect
RAJENDRA LODHAChairperson
Raunika MalhotraWTD
09

Construction Progress

82% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Podiums (if any) 0%
Stilt Floor 0%
10

Amenities

Aggregate area of recreational Open SpaceCommunity BuildingsElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
09

Resale Flats for Sale in Bhiwandi

1
Sanghvi Golden Cityβ‚Ή1.10 Cr
2 BHK Β· 650 sqft
Sanghvi Golden City
πŸ“ Bhiwandi
14

More by Lodha Developers

Lodha Hanging GardensDombivli Β· Under ConstructionLodha OpulisThane Β· Under ConstructionLodha Casa MagnoliaPalava Β· Under ConstructionLodha AureusSewri Β· Under ConstructionLodha Altus Borivali Β· Under ConstructionLodha ElarisVikhroli Β· Under Construction
15

MahaRERA projects nearby in Bhiwandi

Dgt - Sector 3A - Cluster 2 - Phase 11836 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 11025 unitsUsha Residency1020 unitsNarayani Dham Building No 2A And 2B869 unitsDgt - Sector 3A - Cluster 2 - Phase 2830 unitsDgt - Sector 3A - Cluster 2 - Phase 3710 unitsDosti Greater Thane - Sector 3A - Cluster 1B - Phase 3682 unitsSIYARA AVENUE620 unitsMagus City Tower 1 Selene431 unitsSiyara Viva423 unitsArihant Aaradhya Phase Ii412 unitsAtlantic377 units
?

Frequently Asked Questions

When is possession of Upper Thane - Tiara I?

As per MahaRERA, proposed possession is Mar 2024.

Is Upper Thane - Tiara I RERA-registered?

Yes β€” MahaRERA registration P51700018035, registered 2021-09-09. No litigations on record.

Who is the developer?

Lodha Developers β€” 138 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Bhiwandi β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P52000016540β˜… Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK Β· β‚Ή16,946/sq.ft Β· Possession 2026-12-01 00:00:00
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’