Zidane Tower

Stonework Developers
📍 Millat Nagar, Thane · 421302
65
Units
2025
Possession
1
Buildings
Kept in Abeyance
Status
Lifecycle requires verification

Ask an advisor to verify the current project and inventory status.

Source stage: New Project · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01

Possession Timeline

Proposed
Jun 2025
Status
New Project
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Office Space246–548 ft²On request
2 BHK556–891 ft²On request
1 BHK383–1,775 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor
03

RERA Trust Record

MahaRERA No.
P51700027374
Registered
Litigation
No reported in source
Escrow Bank
ICICI BANK
Architect
Waheed Ahmad Hameed Ahmad Ansari
Total FSI
4732
04

Buildings · 1 Wing(s)

Zidane Tower— floors · — units
05

Land DNA · Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06

Location

📍 Millat Nagar
19.312975000000000,73.071453000000000
▸ Explore map & Street View — for verified buyers
07

Promoter & Professionals

STONEWORK DEVELOPERS LLPNA
HK DESIGN CONSULTANTSArchitect
09

Construction Progress

71% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
10

Amenities

Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Water Supply
12

Talk to our MahaRERA advisor

🏠 Discuss what you're looking for📍 Locality & project guidance🤝 Speak to a specialist

Tell our MahaRERA advisor what you need and they'll guide you on this project.

💬 Verify current project inventory
15

MahaRERA projects nearby in Millat Nagar

?

Frequently Asked Questions

When is possession of Zidane Tower?

As per MahaRERA, proposed possession is Jun 2025.

Is Zidane Tower RERA-registered?

Yes — MahaRERA registration P51700027374. The current MahaRERA source record reports no litigations.

Who is the developer?

Stonework Developers

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
WhatsAppEnquire ▸
🎯 AI Matchmaker
Tell us what you want in Millat Nagar — get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
Sponsored
New launch
Akshar Elevate, Vashi
New launch in Vashi — ₹28,895/sq.ft
View project ›

📰 Latest Mumbai Property News

View all news →