ARIHANT ANSHULA

by ARIHANT AASHIYANA PRIVATE LIMITED Company
Certificate SignedP52000009246
๐Ÿ’ฌ WhatsApp๐Ÿ“ž Call

Project Information

RERA Certificate No.
P52000009246
Registration No.
REA52000007948
Registration Date
2019-05-08
Developer
ARIHANT AASHIYANA PRIVATE LIMITED Company
Architect
Kiran K Awhale
Project Bank
ICICI BANK LIMITED
Proposed Possession
2019-12-30
Revised Possession
2019-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
25
Project Area
27390.00 sq.m
Total FSI
26484.00
Approved FSI
26674.00
MahaRERA QR
ARIHANT ANSHULA
MahaRERA โ€” P52000009246
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking21
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking9
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking10
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking6
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking21
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking18
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking13
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking19
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking21
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking13
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking11
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking10
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking10
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking16
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking8
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking18
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking16
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking15
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking13
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking37
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking30
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking13
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking18
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking21
๐Ÿ“…Completion2019-12-30
๐Ÿ—๏ธProposed Floors5
โœ…Sanctioned5
๐Ÿ…ฟ๏ธClosed Parking22
๐Ÿ“…Completion2019-12-30

Apartment Configurations

A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.2624240
100%
SHOP TYPE 127.89110
100%
SHOP TYPE 215.88220
100%
SHOPTYPE321.28110
100%
SHOPTYPE438.93110
100%
SHOPTYPE548.63110
100%

B1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.5516160
100%

B2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.55880
100%
2 BHK46.81880
100%

B3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.5516160
100%

C1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.74440
100%
2 BHK Type I45.34880
100%
2 BHK Type II46.4412120
100%

C2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK45.5824240
100%

C3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK45.8716160
100%

C4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK45.5824240
100%

C5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK30.74440
100%
2 BHK Type I45.34880
100%
2 BHK Type II46.4412120
100%

D1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.9216160
100%

D2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.9216160
100%

D3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.9216160
100%

E1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.5216160
100%

E2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.2424240
100%

E3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.5216160
100%

F1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.91880
100%
2 BHK Type I46.5812120
100%
2 BHK Type II46.66440
100%

F2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.91880
100%
2 BHK Type I46.5812120
100%
2 BHK Type II46.66440
100%

G1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.83880
100%
3 BHK65.22880
100%

G2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.83880
100%
3 BHK65.22871
88%

G3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK Type I47.8412120
100%
2 BHK Type II49.4440
100%
3 BHK62.86880
100%

G4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK Type I47.8412120
100%
2 BHKType II49.4440
100%
3 BHK62.86880
100%

H1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.91880
100%
2 BHK47.5880
100%

H2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK46.5424240
100%

H3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK46.5424240
100%

H4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK46.5424240
100%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk28.90999984741211000
0%
1 Bhk29.90999984741211000
0%
1 Bhk30.739999771118164000
0%
1 Bhk31.239999771118164000
0%
1 Bhk31.520000457763672000
0%
1 Bhk31.549999237060547000
0%
1Bhk31.549999237060547000
0%
2 Bhk45.58000183105469000
0%
2 Bhk45.869998931884766000
0%
2 Bhk46.540000915527344000
0%
2 Bhk46.810001373291016000
0%
2 Bhk47.2599983215332000
0%
2 Bhk47.5000
0%
2 Bhk47.83000183105469000
0%
2 Bhk47.91999816894531000
0%
2 Bhk Type I45.34000015258789000
0%
2 Bhk Type I46.58000183105469000
0%
2 Bhk Type I47.84000015258789000
0%
2 Bhk Type Ii46.439998626708984000
0%
2 Bhk Type Ii46.65999984741211000
0%
2 Bhk Type Ii49.400001525878906000
0%
2 Bhktype Ii49.400001525878906000
0%
3 Bhk62.86000061035156000
0%
3 Bhk65.22000122070312000
0%
Shop Type 127.889999389648438000
0%
Shop Type 215.880000114440918000
0%
Shoptype321.280000686645508000
0%
Shoptype438.93000030517578000
0%
Shoptype548.630001068115234000
0%

Construction Progress

A1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises49%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks33%
Stilt Floor 100%

B1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

B3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

C1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

C2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

C3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

C4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

C5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

D1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

D2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

D3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

E1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

E2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

E3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

F2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

G1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.59%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises69%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

G2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.59%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

G3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.59%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

G4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.32%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

H1

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.27%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

H2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.27%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

H3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

H4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises59%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space90%
โœ…Community Buildings100%
โœ…Electrical Meter Room, Sub-Station, Receiving Station100%
โœ…Energy management100%
โฌœFire Protection And Fire Safety Requirements
โœ…Landscaping & Tree Planting90%
โœ…Open Parking100%
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โœ…Solid Waste Management And Disposal100%
โœ…Storm Water Drains100%
โœ…Street Lighting50%
โœ…Treatment And Disposal Of Sewage And Sullage Water100%
โœ…Water Conservation, Rain water Harvesting80%
โœ…Water Supply100%

๐Ÿ“ฐ Latest Mumbai Property News

View all news โ†’
CallWhatsApp
โœ‰๏ธ

Get in Touch

Our team will connect with you shortly

+91
๐Ÿ”’ Your details are secure with us
โšก If need urgent details +91 98193 11244 for further details.