Birla Vanya Phase 2βœ“ MahaRERA P51700029755βœ“ Clear

Birla Vanya Phase 2 by Century Textiles & Industries

πŸ“ Shahad, Thane Β· 421103
379
Units
2025
Possession
3
Buildings
Certificate Signed
Status
PB
Pooja Batra Β· Senior Advisor
Mumbai Property Exchange Β· MahaRERA-registered since 2017
πŸ“ž CallπŸ’¬ WhatsApp
β˜…Gallery
Birla Vanya Phase 2Birla Vanya Phase 2
iOverview
Birla Vanya is a Residential Project Developed by one of the leading Real Estate Developer Birla Estates. It is located at Kalyan. Kalyan is well-connected by road and rail. It has a major railway station, Kalyan Junction, which is one of the busiest in the Mumbai suburban railway network. This makes it a crucial transit point for commuters traveling to and from Mumbai. Ease of connectivity with an Approximate distance of 2.7 Kms from Kalyan Railway Station and 650M from the Shahad Railway Station. BK Birla School & College at 1.3 Kms. Spread across more than 21 Acres with 7+ Acres of lush green spaces, the new offering at Birla Vanya offers an unparalleled lifestyle for a truly phenomenal experience. 20+ acres gated community from Birla Estates comprising of 2, 3 & 4 BHK LifeDesigned Homes. LEED Gold Rated Pre-Certified Development. 07+ acres of lush greenery. Efficient 3 tier security and fire safety systems. 21 Acres Development Only 7 Towers. 7 Acres Open Green Space and 1.7 Acres Extra Podium Garden. 30+ amenities with 14000++ Sq.Ft. Clubhouse.
01Possession Timeline
Proposed
Mar 2025
Status
New
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
2 BHK640 ftΒ²β‚Ή98 L
3 BHK848–890 ftΒ²β‚Ή1.3 Cr–₹1.36 Cr
4 BHK1,279 ftΒ²β‚Ή1.96 Cr
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700029755
Registered
2021-06-29
Litigation
None on record
Escrow Bank
HDFC BANK
Architect
β€”
Total FSI
45389
04Buildings Β· 3 Wing(s)
Aadhira - Tower E40 floors Β· β€” units
Aruni - Tower C40 floors Β· β€” units
Asita - Tower D35 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Shahad
19.242844800000000,73.153004299999990
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
Century Textiles & Industries LtdNA
Aakar Architects & ConsultantsArchitect
09Construction Progress79% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
10Amenities
Aggregate area of recreational Open SpaceClub HouseElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
15MahaRERA projects nearby in Shahad
Golden City308 unitsTharwani Solitaire Phase Iv208 unitsRoyal Meadows C 1 , C 2188 unitsSunteck Crescent Park -2119 unitsMangalmurti Heights18 unitsBirla Vanya - Phase 11 unitsYashvi ResidencyVardhaman ParkMillenium HeightsPalm PrismSai NirvanaGurudev Orchid
?Frequently Asked Questions
When is possession of Birla Vanya Phase 2?

As per MahaRERA, proposed possession is Mar 2025.

Is Birla Vanya Phase 2 RERA-registered?

Yes β€” MahaRERA registration P51700029755, registered 2021-06-29. No litigations on record.

Who is the developer?

Century Textiles & Industries View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Shahad β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’