List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
πŸ† Mumbai's oldest property portalSince 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
A
βœ“ MahaRERA P51700077627βœ“ Clear

Ambar Vaastu Phase - Ii, C by Balaji Homes

πŸ“ Ambarnath, Thane Β· 421503
112
Units
2027
Possession
1
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Mar 2027
Status
New
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop160–270 ftΒ²On request
1 BHK363–386 ftΒ²On request
1 BHK Landowners363–386 ftΒ²On request
2 BHK Landowners509 ftΒ²On request
2 BHK434–517 ftΒ²On request
3 BHK668–956 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P51700077627
Registered
2024-10-17
Litigation
None on record
Escrow Bank
DCB BANK LIMITED
Architect
Raj Associates
Total FSI
6439
04Buildings Β· 1 Wing(s)
Ambar Vastu Phase-Ii, C-Wing15 floors Β· 112 units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Ambarnath
19.1498672,73.246698
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
BHARAT NARAYAN PATELPartner
DHIRAJLAL RAVACHAND SHAHPartner
ISHWAR NARAYAN PATELPartner
KALPESH DHIRAJLAL SHAHPartner
NIJESH DHIRAJLAL SHAHPartner
PANVELKAR REALTY PRIVATE LIMITED THROUGH ITS DIRECTOR VIJAY RAMCHANDRA PANVELKARPartner
SAMIR TULSHIRAM BHOPIPartner
SATEJ SANJAY DALALPartner
09Construction Progress31% avg
Excavation100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
10Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
14More by Balaji Homes
Balaji HeightsKharghar Β· Sold OutAtlanta EdenworldThane West Β· Sold OutRoyal AccordMalad West Β· Sold Out
15MahaRERA projects nearby in Ambarnath
Pradhan Mantri Awas Yojana - Urban2352 unitsBalaji Uphomes673 unitsMANOHAR VIKAS SHREEJI PARAISO PHASE - 2578 unitsShreeji Milestone575 unitsSky Gardens At Godrej Vihaa495 unitsMohan Willows Iii492 unitsPatels Pristine432 unitsKrushna Vihar - Phase I426 unitsShreeji Square Phase I425 unitsTrident Woods423 unitsShreeji Meadows400 unitsTulsi Viraj394 units
?Frequently Asked Questions
When is possession of AMBAR VAASTU PHASE-II, C-WING?

As per MahaRERA, proposed possession is Mar 2027.

Is AMBAR VAASTU PHASE-II, C-WING RERA-registered?

Yes β€” MahaRERA registration P51700077627, registered 2024-10-17. No litigations on record.

Who is the developer?

Balaji Homes β€” 20 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Ambarnath β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivali
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’